Permit: T17CM04982

Parcel: 11712099A


Addresses:

20 S STONE AV


Inspection Status: Approved

Inspection History: SHEET ROCK NAILING

Permit Number - T17CM04982

Inspection Description - SHEET ROCK NAILING

Inspection Status - Approved

Date Description Inspector Results Comments
05/01/2020 SHEET ROCK NAILING Approved
04/20/2020 SHEET ROCK NAILING Partial Approval Level #1; Section A: corridor walls, public restrooms, amenities room. Ok to tape progress areas.
04/17/2020 SHEET ROCK NAILING Not ready for Inspection RVI
04/16/2020 SHEET ROCK NAILING Not ready for Inspection Contractor cancelled will reschedule for 17 April
03/24/2020 SHEET ROCK NAILING Not ready for Inspection
03/16/2020 SHEET ROCK NAILING Partial Approval Partial. Level #1; Rooms #102; 116; 118. Ok tot tape progress areas.
03/09/2020 SHEET ROCK NAILING Partial Approval Two hour rated double layer sheetrock in Stairwell #1 at Levels #3 to basement; stairwell #2 at Levels 1 to Level #6. Ok to tape progress areas.
03/03/2020 SHEET ROCK NAILING Partial Approval Stairwell #1; at Levels 4 - 7; double layer sheetrock to effect 2 hour rating for stairwell. Ok to tape progress areas.
12/02/2019 SHEET ROCK NAILING Partial Approval Level 2; Area B corridor; Rooms: 309; 310; Level #3 Area B corridor up to Rooms #307-308; Rooms: 415; 416; 417; 419. Ok to tape progress areas.
11/20/2019 SHEET ROCK NAILING Partial Approval Level #3; Section B: Rooms: 302; 303; 304; 305; 306. Ok to tape progress areas.
11/15/2019 SHEET ROCK NAILING Partial Approval Level #2; Room 201.
11/14/2019 SHEET ROCK NAILING Partial Approval Level #3; Rooms: 312; 313; 314; 315; 316; 317; 318; 319, OK to tape progress areas
11/06/2019 SHEET ROCK NAILING Partial Approval Two hour rated elevator shaft at Level #4 to Level #6. Ensure all required areas are fire caulked and taped.
11/05/2019 SHEET ROCK NAILING Partial Approval Elevator shaft at Levels #2 through #4; two hour rated, complete fire caulking.
11/04/2019 SHEET ROCK NAILING Partial Approval Level #2; Rooms: 208, 213, 215. Ok to tape progress areas.
11/01/2019 SHEET ROCK NAILING Partial Approval Level #2; Rooms 203, 204; OK to tape progress areas.
10/31/2019 SHEET ROCK NAILING Partial Approval Level #2; Rooms 202; 206. Ok to tape progress areas.
10/30/2019 SHEET ROCK NAILING Partial Approval Level #2; Room 211. Ok to tape progress areas.
10/29/2019 SHEET ROCK NAILING Partial Approval Level #2; Rooms 212; 213; 215. Ok to tape progress areas.
10/23/2019 SHEET ROCK NAILING Partial Approval rooms #218, 219, 216. Ok to tape progress areas.
09/10/2019 SHEET ROCK NAILING Partial Approval Exterior walls of elevator, first layer. Ok to place second
Layer.
09/06/2019 SHEET ROCK NAILING Not ready for Inspection Contractor cancelled.
08/26/2019 SHEET ROCK NAILING Partial Approval Level #1; corridor #126 one side; Rooms #104 and #104 top-out at 4’ below deck above.
08/22/2019 SHEET ROCK NAILING Partial Approval Level #2; Room wet areas. Ok to tape progress areas.
08/13/2019 SHEET ROCK NAILING Partial Approval Level #4 Electric Room. Ok to tape walls.
08/08/2019 SHEET ROCK NAILING Partial Approval Stairwell #2; Level #5; exterior walls. Level #1; Room #104A, top out at 4 feet from deck above. Ok to tape progress areas.
07/25/2019 SHEET ROCK NAILING Partial Approval Level,#5; Stairwell/Elevator #2. Ok to tape progress areas.
07/10/2019 SHEET ROCK NAILING Partial Approval Elevator shafts #1, 2, 3; two hour rated Sheetrock walls. Ok to tape progress areas.
06/25/2019 SHEET ROCK NAILING Partial Approval Level #4; elevator shaft, exterior walls; ok to tape progress areas
06/21/2019 SHEET ROCK NAILING Partial Approval Stairwell #2; Level #4: double sheeted on exterior walls. Ok to tape progress areas.