Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
Permit Number - T17CM04982
Inspection Description - FRAMING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2020 | FRAMING | Approved | ||
| 04/01/2020 | FRAMING | Partial Approval | Level #1 Office areas, public restrooms. | |
| 03/23/2020 | FRAMING | Not ready for Inspection | ||
| 03/19/2020 | FRAMING | Not ready for Inspection | NR PER ANGEL | |
| 03/09/2020 | FRAMING | Partial Approval | East soffit area | |
| 09/12/2019 | FRAMING | Partial Approval | Level 5 Section A AFT. | |
| 09/10/2019 | FRAMING | Partial Approval | Shear walls on stairwell #1 and elevator area at Level #6. | |
| 09/06/2019 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 08/29/2019 | FRAMING | Partial Approval | Stairwell #1. 2 each shear walls. Ok to install shear walls. | |
| 08/28/2019 | FRAMING | Partial Approval | Level #6 sub-flooring; Section B, nailing and straps in place. | |
| 08/23/2019 | FRAMING | Not ready for Inspection | Section B, Level #6 straps missing on sub deck. | |
| 08/22/2019 | FRAMING | Partial Approval | Level #6 sub.floor system: Section A. | |
| 08/14/2019 | FRAMING | Partial Approval | Level #4; rooms and corridors. | |
| 08/08/2019 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 07/31/2019 | FRAMING | Partial Approval | Level #5; Section A; Shear walls (2). | |
| 07/24/2019 | FRAMING | Partial Approval | Level #5; sub decking at Section B, four each shear walls at stairwell #3. Ok to cover progress areas. | |
| 07/24/2019 | FRAMING | Partial Approval | Level #2, Section "B"; rooms | |
| 07/18/2019 | FRAMING | Partial Approval | Level #5; Section A, sub decking: straps and sheathing nailed In place. |
|
| 07/10/2019 | FRAMING | Not ready for Inspection | Contractor cancelled, called in by mistake. | |
| 06/27/2019 | FRAMING | Partial Approval | Level #4; Shear wall #2; ( 2 of 2). Ok to sheetrock progress areas. | |
| 06/25/2019 | FRAMING | Partial Approval | Level #4; Sub flooring; North portion, in place and nailed. | |
| 06/19/2019 | FRAMING | Partial Approval | Level 4; sub decking all areas except for far North area. Shear walls #2 & 3. Ok to frame sub decking and to sheetrock shear walls | |
| 06/13/2019 | FRAMING | Not ready for Inspection | Contractor cancelled. Will reschedule for 14 June. | |
| 05/28/2019 | FRAMING | Partial Approval | Level #3 sub flooring system: North half. Ok to frame in progress areas. | |
| 05/22/2019 | FRAMING | Partial Approval | Level 3, sub flooring nailed in place; mid section of level. Ok to frame in progress areas. | |
| 05/20/2019 | FRAMING | Partial Approval | Level #3, 3 each shear walls. | |
| 04/30/2019 | FRAMING | Partial Approval | Level #2, 2 each shear walls (Southeast and East) | |
| 01/24/2019 | FRAMING | Partial Approval | Information only. |