Permit: T17CM04982

Parcel: 11712099A


Addresses:

20 S STONE AV


Inspection Status: Approved

Inspection History: EXT METAL CLIPS/EXT SHEATHING

Permit Number - T17CM04982

Inspection Description - EXT METAL CLIPS/EXT SHEATHING

Inspection Status - Approved

Date Description Inspector Results Comments
05/01/2020 EXT METAL CLIPS/EXT SHEATHING Approved
03/09/2020 EXT METAL CLIPS/EXT SHEATHING Partial Approval East soffit area, ESP sheathing. Ok to waterproof and cover.
11/20/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Exterior sheathing at Level #6 and parapet walls on East side of building. Ok to waterproof progress areas.
11/14/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Level #6; Sections A & B interior corridors shear walls. Ok to cover progress areas. ATS Rods in place throughout the floor
10/30/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Level #6, Northwest area exterior sheathing for walls and parapets. Ok to waterproof progress areas.
10/17/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Southwest exterior walls and parapet walls up to mid courtyard area at Level #6. Ok to waterproof progress areas.
10/10/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval South exterior walls at level #6 and parapet walls. Ok to waterproof progress areas
09/23/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval South exterior walls and court yard exterior walls all at Levels #4 & 5. Ok to waterproof progress areas.
09/20/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Levels #4&5; South side and court yard. Ok to water proof exterior system
09/06/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Exterior sheathing on East portion of building at Levels 2-4. Ok to apply waterproofing.
09/03/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Exterior sheathing on East side of structure. Levels #2-4. Ok to water proof and cover progress areas.
08/14/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Exterior sheathing on North and Northwest walls at Levels #2 and #3. Ok to cover progress areas.
07/18/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval South and West exterior walls at Levels #2 and #3. Ok to cover progress areas.
07/05/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Exterior sheathing on South wall at Levels # and #3; Level #4, stairwell #2; North side; Level #3, shear walls in rooms and corridor in Area B. Ok to cover progress areas.
07/03/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Level #3; Section A; shear walls in corridor and rooms up to room #313K. Ok to cover progress areas.
06/28/2019 EXT METAL CLIPS/EXT SHEATHING Partial Approval Level #4; shear wall #2 (1 of 2). Ok to Sheetrock shear wall.
05/31/2019 EXT METAL CLIPS/EXT SHEATHING Not ready for Inspection Level #2, rooms and corridors, Part B. Shear walls in North stairway.