Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM04982

Parcel: 11712099A


Addresses:

20 S STONE AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T17CM04982

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
06/22/2020 EXCAVATION/LAYOUT REBAR & ZON Approved
05/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial (VRI) North courtyard stem al footings for benches and stairs. Ok to place concrete in progress areas.
05/01/2020 EXCAVATION/LAYOUT REBAR & ZON Approved
04/30/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Courtyard planters and bench seating. Ok to pour footings.
04/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Southwest corner of site; extension of ramp and planter walls. Ok to grout progress areas.
02/18/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Planter walls in South and Southwest courtyard areas (30"-56").
Ok to place concrete.
09/06/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #P1; Lobby ramp; Level P3, elevators #1&2 slabs. Ok to place concrete in progress areas.
09/04/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled (ramp area in parking garage)
08/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Elevator slab areas at P1 and P2: Elevator slab and ramp at 4" concrete over hybrid styrofoam in parking garage.
08/13/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Ramp walls in basement to elevators. Ok to place concrete in progress areas.
05/31/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Should have been called as 01020
05/28/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
05/24/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no work
05/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #1, North portion of slab....inspection performed on 31 April, submitted on that date.
04/30/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #1, North half of slab. Ok to place concrete. Rebar in place (concrete over high density styro foam).
04/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #1 slab, #3 rebar reinforcements over high density styrofoam. Ok to place concrete
04/10/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #1, Trash room slab. Ok to place concrete.
04/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Sub-level...P-1 deck. Ok to place concrete.
03/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North half of podium slab OK to pour
03/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Post Tension Cable System on Level #2. North half of slab, #10 Rebar dowels at columns need to be adjusted not to penetrate surface of slab. RFI has been submitted for drill and epoxy correction.
03/20/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Courtesy inspection of North half of Post Tension slab. Will recall when PT System is complete- Level #2.
03/18/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #1 Post Tension Cable System, GL: 1-13.5/G-L. Ok to place concrete.
03/15/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Post tension cable system courtesy inspection. Level #2 Inspection to be scheduled for 18 March
03/12/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Post tension cabling system on deck #1. Contractor cancelled due to rain.
03/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Concrete columns (6 CC3 columns), 3 columns at GL: D/9.5, 12, 15; 3 columns at GL: E/9.5, 12, 15. Ok to place concrete.
03/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear walls #3 and #4 at GL: 10-10.9/H.5-J.5. Ok to place concrete
03/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Concrete Beam #9 at GL: 13/A- ; Column CC1 at GL: B/12. OK to place concrete
03/01/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 each Columns....CC1 at GL: 13/A-B. Ok to place concrete.
02/27/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Toe-down slabs (in fill) Level#1 at GL: 9-10/J.5-G.5. Ok to place concrete.
02/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Catwalk, Revision #2. GL: I.5 - H.5/9 - 10. Ok to place concrete.
02/25/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 7 each columns at GL: CC3 at 9/H.3; CC3 @
at 12/G.4; CC3 at 13/F; 3 columns at CC1 (4) C/10-13; CC1 at 10/C. Ok to place concrete in progress areas.
02/22/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled. Rained out.
02/21/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
02/20/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Catwalk at GL: J.5-H.5/9-10. Ok to place concrete.
02/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 CC1 columns at 3.6/K.5 and 4.5/J .5, CC3 column at 9.6/G .5 ok to pour.
02/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Column CC 1 at gridline j.3/5, column CC 3 at H.3/6.6, tapered column at 8.3/8 shear wall five on Gridline F from 9.7 to 12 all OK to pour.
This was an after hours inspection and was paid from UEB’s APA account.
02/15/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready for inspection. This will be performed as an after hours inspection after 4 PM. Please charge APA $165.
CB 5, 6, 7, 8, 2 and CC 1 GL L 13 ok to pour
02/14/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
02/13/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear wall #1, Columns: 2 each at GL: 13/G-F, 3 each at GL: 12/J.5- G.4. Ok to place concrete. 8’ Turn-down wall at GL: 7-4/K.7-K.2; Columns: 2 each at GL: L/7-8; 3 each at GL: J.5/8-10. Ok to place concrete
02/11/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns CB4-CB4 at GL: K.8/5-6; CC3 at GL: 13/K-J; concrete deck P-1; shear wall #2. Ok to place concrete in progress areas.