Permit: T17CM03512

Parcel: 14043013B

Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T17CM03512

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
09/26/2018 FRAMING Approved
09/19/2018 FRAMING Partial Approval 2 x 4 furrouts level 3 ne & se corridor corners only
09/11/2018 FRAMING Partial Approval Lobby hard lids level 2 only
09/07/2018 FRAMING Not ready for Inspection Lobby area at elevators east only
09/04/2018 FRAMING Partial Approval 1st floor lobby area at elevators
08/22/2018 FRAMING Partial Approval IVRS - Inspection :*
08/06/2018 FRAMING Not ready for Inspection IVRS - Inspection :*
08/01/2018 FRAMING Partial Approval IVRS - Inspection :*
OFFICES 2, 4, 16, 3 & 9 PENDING APPROVED CHANGES
07/17/2018 FRAMING Partial Approval VESTIBLULE 9 ONLY
07/06/2018 FRAMING Not ready for Inspection
07/03/2018 FRAMING Partial Approval IVRS - Inspection :*
ELEVATOR LOBBY 1ST LEVEL
06/25/2018 FRAMING Partial Approval STAIRWELL 1 INT LEVEL ONLY
P1 WALL BATHROOM 1BO110 & 1B0130
06/20/2018 FRAMING Partial Approval HOUSEKEEPING AREA LEVEL 1 & IT CLOSET
AREA A RESTROOMS
FURROUTS BEAMS SOUTH CORRIDOR
06/20/2018 FRAMING Partial Approval INTERIOR WALL WEST OF ELEVATOR
06/19/2018 FRAMING Partial Approval INT. LEVEL LOBBY EAST OF ELEVATOR
06/15/2018 FRAMING Partial Approval ROOMS 1B0295, 1B0275, 1B0130, 1B0255 AND CORRIDOR AREA A
COMPLETION OF OFFICE 9 1ST FLOOR AND OFFICE 10 LEVEL 2
06/14/2018 FRAMING Not ready for Inspection
06/14/2018 FRAMING Partial Approval FURR OUT WALL VESTIBULE # 1 ONLY
06/13/2018 FRAMING Not ready for Inspection cancelled
06/13/2018 FRAMING Partial Approval CAFETERIA ROOM 2A0105
CONFERENCE ROOM 2A0110 AND STORAGE ROOM 2B0105
06/13/2018 FRAMING Partial Approval VESTIBULE 13
06/12/2018 FRAMING Partial Approval level 2 elevator 2 area A
06/08/2018 FRAMING Not ready for Inspection
06/07/2018 FRAMING Not ready for Inspection
06/06/2018 FRAMING Not ready for Inspection
06/04/2018 FRAMING Not ready for Inspection
06/01/2018 FRAMING Partial Approval WEST FUR OUT WALL AT 2ND FLOOR CAFETERIA OK TO COVER
05/31/2018 FRAMING Not ready for Inspection
05/30/2018 FRAMING Not ready for Inspection
05/29/2018 FRAMING Partial Approval INTERSTITIAL ELEVATOR SHFT LINER,FRAMING AND FIRE CAULKING OK TO COVER
05/21/2018 FRAMING Not ready for Inspection
05/18/2018 FRAMING Not ready for Inspection
05/17/2018 FRAMING Partial Approval VESTIBULE POPOUTS IN OFFICES 2,6&8
05/16/2018 FRAMING Not ready for Inspection
05/15/2018 FRAMING Not ready for Inspection
05/14/2018 FRAMING Not ready for Inspection
05/11/2018 FRAMING Partial Approval CAFETETERIA WEST WALL FUR OUT, 2ND FKIIR WEST RESTROOM LIDS
05/10/2018 FRAMING Partial Approval 1ST FLOOR COLUMNS K3-K7, K7-C7 OK
05/09/2018 FRAMING Partial Approval VESTIBULE POPOUTS 3,4,5&7, WING WALLS 1,2,6&8, COLUMNS E1,E2,D2
05/07/2018 FRAMING Not ready for Inspection
05/04/2018 FRAMING Partial Approval 1ST FLOOR OFFICE 1 EAST WALL COMPLETE GRIDLINE B3-B2
05/04/2018 FRAMING Partial Approval 1ST FLOOR GRID 1B-1C
04/30/2018 FRAMING Partial Approval 1ST FLOOR OFFICE 5 WING WALL, VESTIBULE 13-15 POPOUTS, 2ND FLOOR LADIES RESTROOM C CIELING
04/27/2018 FRAMING Partial Approval 2ND FL MENS RESTROOM C FRMAING ELECTIC AND MECHANICAL OK TO COVER, COLUMNS J5,J6,H5,H6 1ST FL VESTIBULE 11 POPOUT, 11 WING WALL OFFICE 12 WING WALL
04/26/2018 FRAMING Partial Approval VESTIBULE POPOUTS OFFICES 12-15
04/25/2018 FRAMING Partial Approval SE STAIRWELL ON 2ND FLOOR
04/24/2018 FRAMING Partial Approval 1s fl vestibule 1, columns c6,c2,f2,e2,g2,d2
04/23/2018 FRAMING Partial Approval 2ND FKIIR VESTIBULE 3
04/20/2018 FRAMING Partial Approval DROP CIELINGS 2ND FLOOR AT NE AND NW CORNER DOORS
04/18/2018 FRAMING Partial Approval 2ND FLOOR COLUMN D5
04/16/2018 FRAMING Not ready for Inspection
04/13/2018 FRAMING Not ready for Inspection NO NEEW WORK
04/13/2018 FRAMING Not ready for Inspection
04/11/2018 FRAMING Partial Approval 1ST FLOOR VESTIBULE,TEAM & CONF 1,SOUTH EXTERIOR WALL K1-D1
04/09/2018 FRAMING Partial Approval VESTIBULES 5,7,&9 POPOUTS
04/06/2018 FRAMING Not ready for Inspection
04/05/2018 FRAMING Partial Approval EXTERIOR STAIR HANDRAILS SHALL EXTEND 12" BEYOND TOP RISER AND CONTINUE SLOPE FOR 1 TREAD DEPTH AT BOTTOM RISER PER IBC1012.5, SND FL VESTIBULE 7 FUROUT
04/04/2018 FRAMING Partial Approval 1ST FLOOR DEMISING,TEAM CONF ROOMS 13,14 &15, OFFICES 6&8 TEAM& CONF ROOMS, GRID LINE D1-D3, COLUMN C4 2ND FLOOR COLUMNS D1,D2,E2,H1,H2,J2,G4 ESTERIOR WALL A1-A2-A1-B1
04/02/2018 FRAMING Cancelled
03/29/2018 FRAMING Partial Approval 1ST FLOOR RESTROOMS B, OFFICE 9 VESTIBULE AND CONFERENCE, JANITORS CLOSEST,ELECTRIC ROOM B, VESTIBULES 7,5,4,3 AND LARGE CONFERENCE ROOM
03/28/2018 FRAMING Not ready for Inspection
03/27/2018 FRAMING Not ready for Inspection
03/26/2018 FRAMING Partial Approval 1ST FL C3-C4 C-H, N&W WALLS ELECTRIC ROOM 2ND FLOOR VESTIBULES 12,13 COLUMN C3, CAFE S&W WALLS
03/25/2018 FRAMING Not ready for Inspection
03/22/2018 FRAMING Partial Approval 1ST LOOR EAST WALL ROOM 1F0400 BEAM FUR OUT RM 1B0315
03/21/2018 FRAMING Partial Approval 1ST FLOOR VESTIBULES 11,12,13 OFFICES 10,11,12,7 NCIT,CLASSIFIED AND ELECTRIC ROOMS OK
03/19/2018 FRAMING Partial Approval VESTIBULES 6 AND 4, WALL GRID LINE B2.5 ATOB
03/16/2018 FRAMING Partial Approval 1st floor a3-c3 ok
03/15/2018 FRAMING Partial Approval 2nf loor office 4 vestibule, office 19 wing walls,exterior walls a2.5-a1.5 a1-b1 columns g7, k3-k7 restroom b plumbing chase walls
03/15/2018 FRAMING Partial Approval 1st floor south wall north corridor k7-g7
03/14/2018 FRAMING Partial Approval 1st floor a3-a4 a3-c3 ok
03/12/2018 FRAMING Partial Approval vestibules for offices 7,9 &10
03/12/2018 FRAMING Partial Approval 2nd floor vestibules 1,3,4,7,9,10
03/07/2018 FRAMING Cancelled
03/05/2018 FRAMING Partial Approval nd floor west restroom plumbing cahse walls, beam fur out south side j4-k4
03/02/2018 FRAMING Partial Approval 2nd floor b3 and b4 columns, east restooms plumbing chase walls and north wall fur out, beam fur out rooms c0505 b0455, 1st floor h5-k5 k6-k4
03/01/2018 FRAMING Partial Approval wing walls in 2j0600 2h0600, columns e3,f3,g3,h3 and j3
02/28/2018 FRAMING Partial Approval 1st floor soffitt g7-k7, west wall k3-k7 2nd floor columns c5,d6,b6 and a6, office 17 &18 vestibles
02/26/2018 FRAMING Partial Approval 2nd fl columns g4,g6,f6,e6,f4,g2,f2,e2,b3,b4,k7-d7 east exterior wall a5-a3. 1st fl c7-f7 south side south wall of north corridor
02/23/2018 FRAMING Partial Approval rm 19 offset at beam, gridline c1-c2 , d6 column vestibule room 2d02 200a
02/22/2018 FRAMING Partial Approval 1st floor locations marked on plans
02/21/2018 FRAMING Partial Approval large conf rm 1 d4 line ok office 19 east and south walls office 19 3 columns on northside
02/15/2018 FRAMING Partial Approval 1st floor a7-b.5 7, c7-c7 b,5- c4 to c7 except wall between ncit and south team room
02/09/2018 FRAMING Partial Approval 2nd floor electric rooms ok
02/09/2018 FRAMING Cancelled
02/08/2018 FRAMING Not ready for Inspection
02/07/2018 FRAMING Partial Approval
02/07/2018 FRAMING Partial Approval 2nd floor grids f3-d2.5
02/06/2018 FRAMING Partial Approval 2nd floor k2-kt , f2-f1, ji-c1 approved
02/02/2018 FRAMING Partial Approval area c grid lines c-k 3-7 marked in orange on plans ok
02/01/2018 FRAMING Partial Approval 2nd level north exterior wall approved
01/23/2018 FRAMING Partial Approval area c top floor mrked on plans in blue, middle floor c1-j1 and a7-a3 provide specs on sole plate attachment ok to hang 1 side
01/22/2018 FRAMING Partial Approval INTERSTITIAL FLOOR NORTH WALL FURR OUT PER DETAIL 1/A3.31 WALL SECTION
GRID LINE 7 FROM A-K AND WEST WALL GRID LINE K FROM 2-7
OK TO COVER