Inspection Status: Passed
Inspection History: COT - RSEL - Grounding/Bonding
| Date |
Description |
Inspector |
Results |
Comments |
| 02/03/2020 |
COT - RSEL - Grounding/Bonding |
DQUINN |
Approved |
Entered by DMERANZ1 - |
| 01/30/2020 |
COT - RSEL - Grounding/Bonding |
TVALENCIA |
Denied |
Entered by DMERANZ1 - 1- Shall provide 18 inches of cover from top of conduit piping to finish grade.
Reference Table E3803.1 2012 IRC |
| 05/17/2019 |
COT - RSEL - Grounding/Bonding |
TVALENCIA |
Partial Approval |
Entered by CBELL1 - 1- 20 feet of copper #4 Ufer conductor provided in footing. |
| 05/14/2019 |
COT - RSEL - Grounding/Bonding |
TVALENCIA |
Partial Approval |
Entered by CBELL1 - 1- Shall complete forms for footing and slab.
2- Reference footing detail 1 S-1 showing the top rebar.
3- Shall wrap plumbing risers and any plumbing in concrete.
4- 20 feet of copper Ufer has been provided. |