Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 10/21/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :* |
| 10/20/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 4TH 4' LIFT AT S.E. ENTRY. |
| 10/19/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 10/18/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 3RD. 4' LIFT AT CMU WALL AT S.E.ENTRY PENDING SPECIAL INSPECTION. |
| 10/13/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 2ND 4' LIFT. |
| 10/12/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CHECKED REINFORCING STEEL AT S.E. ENTRY. OK TO GROUT 1ST 4' LIFT. |
| 10/11/2016 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO POUR STEM WALL AT S.E. ENTRY. |