Inspection Status: Approved
Inspection History: PLUMBING - ROOF DRAINS
| Date |
Description |
Inspector |
Results |
Comments |
| 09/22/2017 |
PLUMBING - ROOF DRAINS |
|
Approved |
|
| 06/20/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
PRIMARY AND OVER-FLOW DRAINS AT SOUTH STAIRWELL AT LEVELS #3 - 1. |
| 03/12/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
LEVEL #2; PRIMARY DRAIN AT GL: 17/CE |
| 03/09/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
ROOF DRAINS AT LEVEL #1: PRIMARY AND OVER-FLOW: GL: CE/17 |
| 03/08/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
LEVEL #2: PRIMARY AND OVER-FLOW DRAINS AT GL: CE/15. |
| 03/07/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
ROOF DRAINS AT LEVEL #2: NORTH RAMP SIDE: PRIMARY AND OVER-FLOW ROOF DREAINS AT GL: BE/15. SOUTH RAMP SIDE AT GL: 13/CE; PRIMARY AND OVER FLOW ROOF DRAINS. |
| 03/03/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
PRIMARY AND OVER-FLOW DRAINS AT LEVEL #2; GL: CE/11 |
| 03/01/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
PRIMARY AND OVER-FLOW DRAINS AT GL: CE/17; BE/17; BW/11 |
| 02/16/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
LEVEL #2, NORTH WEST SECTOR:4 EACH OVER-FLOW DRAINS. |
| 02/15/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
PRIMARY ROOF DRAINS AND OVER FLOW DRAINS ON LEVEL 2; NORTH WEST SECTION OF GARAGE. |
| 02/14/2017 |
PLUMBING - ROOF DRAINS |
|
Partial Approval |
ROOF DRAINS AT SOUT EAST PORTION OF PARKING STRUCTURE; 4 ROOF DREAINS AND 4 OVER FLOW DRAINS. |