Permit: T16CM06577

Parcel: 11202003D


Addresses:

3838 N CAMPBELL AV

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
09/22/2017 BUILDING - PROGRESS Approved
05/01/2017 BUILDING - PROGRESS Partial Approval RETAINING WALL FOOTING AT NORTH SIDE OF PARKING STRUCTURE, GL: AW/1 - 18. OK TO PLACE CONCRETE.
03/21/2017 BUILDING - PROGRESS Partial Approval ELECTRIC TEMPORARY POWER. POWER FROM CANCER CENTER TO PARKING STRUCTURE ELECTRIC ROOM (PANEL 1) TO MEDICAL CENTER PANELS: PT1; PT2-A; PT3-B. OK TO ENERGIZETEMPPOWER SYSTEM.
03/02/2017 BUILDING - PROGRESS Partial Approval ROOF DRAINS: LEVEL #2, GL: 13/BE (PRIMARY), LEVEL #1 GL: 13/BE (PRIMARY)
02/06/2017 BUILDING - PROGRESS Partial Approval CMU WALLS AT 16' - 20': S.E. STAIRWELL, S.W. STAIRWELL, ELEVATOR AREA. OK TO GROUT PROGRESS AREAS.
02/03/2017 BUILDING - PROGRESS Not ready for Inspection
01/25/2017 BUILDING - PROGRESS Partial Approval CMU WALLS AT SE STAIRS AT 17'4"; SW STAIRWELL AND ELEVATOR AREA AT LIFT 3 - 4. OK TO GROUT PROGRESS AREAS.
01/24/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #2, SLAB AT GL: CW.5 - CW/9 - 18. OK TO PLACE CONCRETE.
01/23/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: SE STAIRWELL AT 12' - 16' GL: CE.8 -DE/ 18; ELEVATOR WALLS (E, W,N) AT 8' - 12'; SW STAIR WELL WALL AT 12' - 16' (NORTH WALL), GL 1/CW.5. OK TO GROUT PROGRESS AREAS.
01/20/2017 BUILDING - PROGRESS Partial Approval NOT READY - RAMP SLAB AT 3 - 2.5
01/12/2017 BUILDING - PROGRESS Partial Approval LEVEL #2: SLABS #1 AND #3 HAVE BEEN POURED.
01/11/2017 BUILDING - PROGRESS Partial Approval LEVEL #2; SLAB #1; OK TO PLACE CONCRETE.
01/10/2017 BUILDING - PROGRESS Partial Approval PRE-SLAB: LEVEL #2; SLABS 3 AND 4; CLEAN PROGRESS AREAS. OK TO PLACE CONCRETE.
12/28/2016 BUILDING - PROGRESS Partial Approval PRE-SLAB: LEVEL #1; SLAB #3 GL: 5.8 -8/AW - DW. OK TO PLACE CONCRETE
12/27/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING AND ELECTRIC UNDERGROUND NOT READY FOR INSPECTION.