Inspection Status: Partial Approval
Inspection History: SITE - SEWER
| Date |
Description |
Inspector |
Results |
Comments |
| 10/10/2016 |
SITE - SEWER |
|
Partial Approval |
MAN HOLE #5; PREPPED AND GROUTED. OK TO ACIVATE. |
| 10/07/2016 |
SITE - SEWER |
|
Partial Approval |
MAN HOLE #1 - PIPE CUT AND PATCHED. OK TO ACTIVATE |
| 09/02/2016 |
SITE - SEWER |
|
Partial Approval |
MANHOLE TEST AT MH #1 - 5, PRESSURE TESTED, LATERALS OBSERVED BY ENGINEER OF RECORD (DIBBLE; GREG). RESULTS OF TESTING TO BE FORWARDED TO THIS OFFICE. |
| 09/01/2016 |
SITE - SEWER |
|
Partial Approval |
8" WATER LINE (APPROXIMATELY 160') GL: 20 NORTH. OK TO COVER PROGRESS AREA. |
| 08/31/2016 |
SITE - SEWER |
|
Partial Approval |
8" WATER LINE (APPROXIMATELY 184') AT GL: A (NORTH) TO GL: 16 - 20; LATERALS (20' NORTH AND SOUTH) AT GL: 20 EAST. OK TO COVER PROGRESS AREAS. |
| 08/30/2016 |
SITE - SEWER |
|
Partial Approval |
INFORMATION: SET UP MANHOLE INSPECTION (5) FOR 2 SEPTEMBER AT 0830 HOURS |
| 08/24/2016 |
SITE - SEWER |
|
Partial Approval |
MAN HOLE #4 - FORMED AND COMPLETE. 8" WATER LINE; APPROXIMATELY 575' (NORTH OF PARKING STURCTURE TO EAST END; SOUTH TO AREA BETWEEN BUILDING AND PARKING STRUCTURE: OK TO COVER PROGRESS AREAS. |
| 08/24/2016 |
SITE - SEWER |
|
Partial Approval |
8" SEWER LINE (APPROXIMATELY 75") GL: 20/A EAST. OK TO COVER PROGRESS AREA. |
| 08/11/2016 |
SITE - SEWER |
|
Not ready for Inspection |
RAINED OUT |
| 08/09/2016 |
SITE - SEWER |
|
Not ready for Inspection |
RAINED OUT |
| 07/29/2016 |
SITE - SEWER |
|
Partial Approval |
8" SEWER LINE EAST OF MH #3, APPROXIMATELY 35', MH #3 WALLS COMPLETE: OK TO COVER PROGRESS AREA |
| 07/28/2016 |
SITE - SEWER |
|
Partial Approval |
LATERAL TO MH #4, APPROXIMATELY 25' NE OF BUILDING |
| 07/26/2016 |
SITE - SEWER |
|
Not ready for Inspection |
|
| 07/22/2016 |
SITE - SEWER |
|
Partial Approval |
LATERAL LINE TO MH #3 - APPROXIMATELY 50'; BASE FOR MH #2 POURED |
| 07/22/2016 |
SITE - SEWER |
|
Partial Approval |
8" LATERAL SEWER LINE TO MAN HOLE #3, APPROXIMATELY 75'. OK TO COVER PROGRESS AREA. |
| 07/21/2016 |
SITE - SEWER |
|
Partial Approval |
8' SEWER LINE FROM MAN HOLE #2 EAST FOR APPROXIMATELY 100', OK TO COVER PROGRRESS AREA |
| 07/19/2016 |
SITE - SEWER |
|
Partial Approval |
8" SEWER LINE FROM MH #1 TO EAST; APPROXIMATELY 200'. OK TO COVER PROGRESS AREAS. MAN HOLE#1: WALLS POURED |
| 07/19/2016 |
SITE - SEWER |
|
Partial Approval |
8' SEWER LINE FROM MAN HOLE #2, EAST APPROXIMATELY 100' OK TO COVER PROGRESS AREA |