Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T16CM03514

Parcel: 11202003D

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Date Description Inspector Results Comments
04/11/2019 ELECTRIC - INTERMEDIATE Approved
09/26/2018 ELECTRIC - INTERMEDIATE Partial Approval MRI-3T, Rooms # 1A117, 1A118. Ok to cover walls
09/21/2018 ELECTRIC - INTERMEDIATE Partial Approval PET-CT ROOMS #140 through #145.
01/10/2018 ELECTRIC - INTERMEDIATE Not ready for Inspection FRAMING STUD NEEDS TO BE MOVED (HCR #3) AWAY FROM ELECTRIC CONDUIT TO ALLOW FOR PROPER INSTALLATION OF SHEETROCK.
12/07/2017 ELECTRIC - INTERMEDIATE Partial Approval SPOT CHECKED GFCI OUTLETS ON LEVELS #1, 2, 3. NO PROBLEMS WERE FOUND.
12/06/2017 ELECTRIC - INTERMEDIATE Partial Approval OVER HEAD LIGHTING IN LINAX #1 AND LINAX #2.
11/17/2017 ELECTRIC - INTERMEDIATE Partial Approval LINAC #3, CONTROL ROOM #AB217 - ELECTRIC IN WALLS. OK TO COVER WALLS.
11/13/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC IN WALLS IN LINAC #3, OK TO COVER WALLS.
11/06/2017 ELECTRIC - INTERMEDIATE Partial Approval LINAC #2, LINAC CORRIDOR, CONTROL ROOMS #1B237, 1B232; CAMERA ROOMS #1A136, 1A137 (SOUTH AND WEST WALLS); IN WALL ELECTRICITY.
10/26/2017 ELECTRIC - INTERMEDIATE Partial Approval IN WALL ELECTRIC AT LINAC #1. OK TO COVER WALLS.
10/10/2017 ELECTRIC - INTERMEDIATE Partial Approval E;ECTRIC PANELS: LEVEL #1: LPW1A, 1B, 1C; LEVEL #2: LPE2A, 2B, 2C; LEVEL #3 LPE3C. OK TO ENERGIZE PANELS.
09/26/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC PANELS #HMP-1, HMP-2, HMP-3, LE -3. OK TO ENERGIZE PANCELS.
09/25/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC PANELS #LMW1, LMW2, LMW3. OK TO ENERGIZED PANELS.
09/22/2017 ELECTRIC - INTERMEDIATE Cancelled
09/05/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL #1, PANEL #LME-1; LEVEL #2, PANEL #2, LME-2. OK TO ENERGIZE PANEL LME-1. LEM-2 TO BE ENERGIZED AT A LATER DATE.
08/25/2017 ELECTRIC - INTERMEDIATE Cancelled
08/24/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL #2, PANEL HLE -2; OK TO ENERGIZE PANEL FRO LEVELS #1 & 2; LOCK OUT, TAG OUT MUST BE USED IN THIS PANEL.
08/22/2017 ELECTRIC - INTERMEDIATE Partial Approval LIGHT POLE CAISSONS: ALLEN ROAD (4), PARKING STRUCTURE (2). OK TO PLACE CONCRETE.
08/21/2017 ELECTRIC - INTERMEDIATE Cancelled
08/17/2017 ELECTRIC - INTERMEDIATE Partial Approval UTILITY PLANT, ELECTRIC PANEL #PCP- MSD-1 AT 1200 AMPS. OK TO ENERGIZE.
08/16/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL #3, ELECTRIC IN WALLS: GL: C - H/7 - 12. OK TO COVER WALLS.
08/11/2017 ELECTRIC - INTERMEDIATE Partial Approval
08/11/2017 ELECTRIC - INTERMEDIATE Cancelled
08/07/2017 ELECTRIC - INTERMEDIATE Cancelled
08/03/2017 ELECTRIC - INTERMEDIATE Cancelled
08/02/2017 ELECTRIC - INTERMEDIATE Cancelled
08/01/2017 ELECTRIC - INTERMEDIATE Cancelled
07/31/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC IN WALLS AT GL: D - H/12 - 14.5 ON LEVEL #3.
07/26/2017 ELECTRIC - INTERMEDIATE Cancelled
07/25/2017 ELECTRIC - INTERMEDIATE Cancelled
07/24/2017 ELECTRIC - INTERMEDIATE Cancelled
07/21/2017 ELECTRIC - INTERMEDIATE Cancelled
07/20/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC ROOM #1A218: PANELS: LME-1, HLE-1, LPE-1B, LPE-1A, GDPPE. OK TO ENERGIZE PANELS.
07/18/2017 ELECTRIC - INTERMEDIATE Partial Approval AREAS 11 - 14; GL: 5 - 9/C - G: ELECTRIC IN WALLS, OK TO ON SIDE SHEET ROCK.
07/17/2017 ELECTRIC - INTERMEDIATE Cancelled
07/14/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC UNDERGROUND - SIX CAISSON LIGHT POLE FOOTINGS WITH 3/4" CCONDUIT LINES.
07/13/2017 ELECTRIC - INTERMEDIATE Cancelled
07/12/2017 ELECTRIC - INTERMEDIATE Cancelled
07/12/2017 ELECTRIC - INTERMEDIATE Cancelled
07/11/2017 ELECTRIC - INTERMEDIATE Cancelled
07/10/2017 ELECTRIC - INTERMEDIATE Cancelled
07/07/2017 ELECTRIC - INTERMEDIATE Partial Approval POLE LIGHT CAISSONS; 6 @ PARKING SRUCTURE; 3 @ ALLEN CENTER. OK TO POUR CAISSON FOOTINGS.
07/05/2017 ELECTRIC - INTERMEDIATE Cancelled
06/29/2017 ELECTRIC - INTERMEDIATE Cancelled
06/23/2017 ELECTRIC - INTERMEDIATE Cancelled
06/22/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC IN WALLS IN ROOMS AT GL: D - G/8 - 10
06/20/2017 ELECTRIC - INTERMEDIATE Cancelled
06/19/2017 ELECTRIC - INTERMEDIATE Cancelled WORK INCOMPLETE.
06/16/2017 ELECTRIC - INTERMEDIATE Cancelled
06/15/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL 3 ELEVATOR 1,2,3,4 CONTROL PANELS OK.
06/14/2017 ELECTRIC - INTERMEDIATE Cancelled
06/13/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE.
06/12/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL #2: GL: D - H/10 - 12. OK TO COVER WALLS.
06/09/2017 ELECTRIC - INTERMEDIATE Partial Approval UNDERGROUND CONDUITS AT NORTH OF TRASH ENCLOSURE: 2 @ 3/4" CONDUITS. OK TO COVER PROGRESS AREA.
06/08/2017 ELECTRIC - INTERMEDIATE Partial Approval DISCONNECTS FOR AIR HANDLERS #1 & #2.
06/07/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
06/06/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
06/02/2017 ELECTRIC - INTERMEDIATE Partial Approval PARTIAL. INFORMATION. ROOD LEVEL: LOCATION OF FEEDER LINES TO AIR HANDLERS # 1 & #2.
06/01/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection RESCHEDULED FOR 2 JUNE
05/31/2017 ELECTRIC - INTERMEDIATE Partial Approval EMERGENCY GENERATOR; TRANSFER SWITCHES: DP-HELV; APS-ELV ON LEVEL #1. LEVEL #2, PANEL MDPE3.
05/30/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/29/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/25/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/24/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE.
05/23/2017 ELECTRIC - INTERMEDIATE Partial Approval LEVEL #2, ROOMS IN AREA AT GL: E - H/12 - 15.
05/22/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE.
05/19/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE.
05/18/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/17/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/16/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection WORK INCOMPLETE
05/15/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC ROOM #10185, SES UNITS #1 AND #2; MSB #1 AND MSB #2. OK TO ENERGISE UNITS.
05/12/2017 ELECTRIC - INTERMEDIATE Partial Approval AREAS #1 - 4, LEVEL #2; GL: C - G/15 - 19
05/11/2017 ELECTRIC - INTERMEDIATE Partial Approval BOXES AND SWITCHES IN ROOMS AT GL: C - G/4 - 7. OK TO INSULATE AND COVER WALLS.
05/10/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection
05/09/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection
05/08/2017 ELECTRIC - INTERMEDIATE Partial Approval X-FORMER IN GARAGE FIRST FLOOR OK TO CLOSE.
05/05/2017 ELECTRIC - INTERMEDIATE Cancelled
05/04/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection
05/03/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection
05/02/2017 ELECTRIC - INTERMEDIATE Not ready for Inspection NOT READY
04/28/2017 ELECTRIC - INTERMEDIATE Partial Approval AREAS 3, 4, 5, 6.
04/21/2017 ELECTRIC - INTERMEDIATE Partial Approval IFORMATION ONLY: RE: ADDITIONAL LUGS FOR SES CABINET.
03/14/2017 ELECTRIC - INTERMEDIATE Partial Approval PRELIMINARY WALK THROUGH: SWITHCH BOXES, OUTLET BOXES, FIRER ALARM BOXES, DATA BOXES, LOW VOLTAGE BOXES IN AREAS AT GL: F/8 - 20; D - H/8 - 20. ALL AREAS TO BE RECHECKED WHEN NEEDED MATERIALS ARRIVE.
01/19/2017 ELECTRIC - INTERMEDIATE Partial Approval 4" CONDUITS INTO EACH VAULT (4 CONDUITS PER VAULT, 4 VAULTS