Permit: T16CM03514

Parcel: 11202003D

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
04/11/2019 BUILDING - FINAL Approved Approved pending Engineering finals.
01/07/2019 BUILDING - FINAL Not ready for Inspection need to complete all assigned inspections
08/07/2018 BUILDING - FINAL Partial Approval LEVEL 1, MRI ROOM #1: TO BE CONSIDERED UNDER THE JURISDICTION OF CURRENT TEMPORARY CERTIFICATE OF OCCUPANCY: OK TO OCCUPY AND ADMINISTER TO PATIENTS IN THIS AREA.
05/24/2018 BUILDING - FINAL Partial Approval IMAGING ROOMS ON LEVEL #1, EAST PORTION OF BUILDING AT GL: 17-20/D-H. OK TO OCCUPY AND TREAT PATIENTS IN THIS AREA. THIS AREA IS TO BE ADDED TO TEMPORARY CERTIFICATE OF OCCUPANCY: DATED 12-14-17
03/28/2018 BUILDING - FINAL Partial Approval LEVEL #1; EAST AND WEST PORTIONS: AREA "A" AND AREA "C"; GL: C/2-8, 8/C-F.5. APPLICATION MADE TO INCLUDE AREAS INTO CURRENT TEMPORARY CERTIFICATE OF OCCUPANCY.
12/21/2017 BUILDING - FINAL Partial Approval NEED ADDRESSING FOR BUILDINGS #1 AND #2.
12/12/2017 BUILDING - FINAL Partial Approval INFORMTION FOR TCO REQUIREMENTS.
12/11/2017 BUILDING - FINAL Partial Approval INSPECTIONS FOR TEMPORARY CERTIFICATE OF OCCUPANCY - OK TO OCCUPY BUILDING, PENDING RECEIPT OF CHLORINATION REPORT.
12/08/2017 BUILDING - FINAL Not ready for Inspection MET WITH PROJECT MANAGER TO DISCUSS DISCREPANCIEN OF TCO WALK THROUGH OF 6 DEC 17. TCO WALK THROUGH IS SCHEDULED FOR 11 DEC 17 AT 1230 HOURS.
12/07/2017 BUILDING - FINAL Not ready for Inspection TCO WALK THROUGH: DISCREPANCIES NOTED WITH H-P PERSONNEL. FOLLOW UP WALK THROUGH TO BE SHCEDULED FOR APPROXIMATELY 11 DEC 17