Permit: T16CM03514

Parcel: 11202003D

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
04/11/2019 BUILDING - PROGRESS Approved
01/05/2018 BUILDING - PROGRESS Partial Approval ABOVE CEILING: ELECTRIC, PLUMBING, MECHANICAL IN AREAS "A" AND "C" ON LEVEL #1; LINAX #4 ABOVE. OK TO PLACE CEILING GRID AND TILES.
12/04/2017 BUILDING - PROGRESS Partial Approval PRE-TCO WALK THROUG. SCHEDULED FINAL WALK THROUGH (TCO) FOR 0900 6 DECEMBER 2017.
11/29/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: AMBULANCE PAD - OK TO PLACE CONCRETE.

SHEETROCK NAILING: LINAC #3 CONTROL ROOM #1B203, LINAC #4 CONTROL ROOM #1B217. OK TO TAPE PROGRESS AREAS.
11/06/2017 BUILDING - PROGRESS Partial Approval THIS INSPECTION SHOULD FALL UNDER THE PERMIT OF DP16-0030. THERE ISN'T AN AREA TO RECORD THE FOLLOWING INSPECTION: SOUTH PARKING LOT (SURFACE LOT); LIGHT POLE CAISSON FOOLTINGS AN CAGES IN PLACE -6 FOOTINGS. OK TO PLACE CONCRETE.
10/23/2017 BUILDING - PROGRESS Partial Approval 2 FOOT BRIDGE FOOTINGS AT SOUTH WEST PARKING STRUCTURE AREA (POURED). BRIDGES WILL NEED HAND RAILS.
09/27/2017 BUILDING - PROGRESS Cancelled
09/19/2017 BUILDING - PROGRESS Partial Approval PARKING STRUCTURE ; ELECTRIC ROOM DOORS (3) ARE SECURED.
09/18/2017 BUILDING - PROGRESS Partial Approval 3 FOOTINGS AT AMBULANCE CANOPY OK TO POUR
09/06/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: ELECTRIC ENCLOSURE, CMU WALLS AT 72' (TOP OUT). OK TO GROUT. ***NOTE: RONALD McDONALD HOUSE - TRASH ENCLOSURE - CMU WALLS TOPPED OUT AT 72".
09/01/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: ENERGENCY GENERATOR ARE - TOPPED OUT AT 10' 4". GROUTED AND CAPPED.
08/30/2017 BUILDING - PROGRESS Partial Approval MECHANICAL, ELECTRICAL, PLUMBING: LEVEL #2, ROOMS AT GL: G/17 - 19. OK TO SET CEILING TILES.
08/22/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: GENERATOR ENCLOSURE - CMU WALLS AT 0" - 48". ELECTRIC EQUIPMENT AREA - CMU WALLS AT 0" - 56". OK TO GROUT PROGRESS AREAS.
08/14/2017 BUILDING - PROGRESS Partial Approval ROOMS ABOVE CEILINGS (MEP); LEVEL #5, TOWER 5, ROOMS #1 - 12, 12 - 24; ROOMS: 0550001; 05500111, 0550124A, . LEVEL #5, TOWER 4; LDR-2, LEVEL 6, TOWER 5; PATIENT ROOMS 12 - 24.
08/03/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: BENCH SEAT, WEST OF BRIDGE; DETAIL #2, PAGE #L402. STRAIGHT SEAT WALL, NORTH OF 5' BRIDGE; DETAIL #3, PAGE L402. OK TO PLACE CONCRETE FOR SEATS.
07/20/2017 BUILDING - PROGRESS Partial Approval EXCAVATION LAYOUT/REBAR: TWO CMU WALL/BENCH FOOTINGS WEST OF PARKING STRUCTURE - AS PER PLAN. OK TO PLACE CONCRETE.
07/20/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR; DETAILS #2 - 3, PAGE S8.01, EMERGENCY GENERATOR ENCLOSURE FOOTING: NORTH WALL (10'), SOUTH WALL (6'). OK TO PLACE CONCRETE.
07/14/2017 BUILDING - PROGRESS Partial Approval SIX CAISSON LIGHT POLE FOOTINGS; 2 FOOTING FOR BRIDGES (EAST OF PARKING STRUCTURE) O, TO POUR PROGRESS AREAS.
04/27/2017 BUILDING - PROGRESS Partial Approval EXTERIOR FRAMING AT GL: 2/C - G, LEVELS 1, 2, 3, ROOF PARAPET. OK TO INSULATE AND COVER
04/06/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT GL: D/17 - 18; AT 32' - 36'. OK TO GROUT PROGRES AREA.
03/23/2017 BUILDING - PROGRESS Partial Approval INFORMATION: PERMISSSION GRANTED TO ONE-SIDE SHEET ROCK FOR INTERIOR WALLS.
03/21/2017 BUILDING - PROGRESS Partial Approval LEVEL #2: TEMPORARY RESTROOMS - PLUMBING AND ELECTRIC ARE GOOD. OK TO COVER WALLS.
03/15/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT 28" - 32" AT STAIRWELL #2. OK TO PLACE GROUT.
EXCAVATION/LAYOUT REBAR: PEDISTAL CAPS AT GL: D/4 - 9; F/4 - 9; 4/C - F. OK TO PLACE GROUT.
03/14/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT 24' - 28' AT STAIRWELL #2. OK TO GROUT PROGRESS AREA.
03/13/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT STAIRWELL #2; AT 20' - 24'. OK TO PLACE GROUT. EXCAVATION/LAYOUT REBAR: PARTIAL: ROOF LEVEL: PIER CAPS (20), GL: D/8 - 18; F/ 8 - 18. OK TO PLACE CONCRETE.
03/12/2017 BUILDING - PROGRESS Partial Approval LINAX #1 AND #3: DOOR AREAS -OK TO PLACE CONCRETE
03/09/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT STAIRWELL #2 - 16' - 20'. OK TO GROUT PROGRESS AREA. EXCAVATION/REBAR AND LAYOUT: ROOF LEVEL: PIER CAPS (9) AT GL: D.5/8.75 - 9.75; 9.3 - 10.3/ F.5. OK TO PLACE CONCRETE..
03/06/2017 BUILDING - PROGRESS Partial Approval SHEET ROCK NAILING: EXTERIOR SHEATHING AT LEVELS 1 - 3 GL: H/12 - 14. OK TO WATER PROOF PROGRESS AREA. LINAX: EXTERIOR WALLS: EAST, NORTH, WEST. OK TO WATER PROOF PROGRESS AREAS.
03/03/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALL AT STAIRWELL #2, COLORED WALL AT 12' - 16'. OK TO GROUT PROGRRESS AREA.
03/02/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: STAIRWELL #2, CMU WALL (COLORED) AT 8' - 12'. OK TO GROUT PROGRESS AREA. ROOD NAILING: MAIN ENTRY CANOPY - METAL DECKING: PUDDLE WELDED AND CRIMPED. BUILDING PRE-SLAB: SLAB AT ROOF LEVEL GL: C - H/ 1 - 8. OK TO PLACE CONCRETE.
03/01/2017 BUILDING - PROGRESS Partial Approval MECHANICAL ABOVE CEILING: ROUGH-IN DUCT WORK; MEDIUM PRESSURE, SUPPLY, EXHAUST: LEVEL #1, GL C - E/2 - 10; LEVEL #2: B - H/10 - 14.
02/24/2017 BUILDING - PROGRESS Partial Approval LEVEL #4 SLAB AT GL: 6.5 - 10/B - G. OK TO PLACE CONCRETE
02/24/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: STAIRWELL #2, AT 4' - 8'. OK TO GROUT PROGRESS AREA.
02/21/2017 BUILDING - PROGRESS Partial Approval EXTERIOR FRAMING AT GL: 1/A - E.5; A/1 - 3.5; 3.5/A - C; E.5/1 - 2. OK TO COVER WALLS. LEVEL #3 - COLUMNS AT GL: 0 - 1/C, D, E; SHEAR WALL AT GL: C/7 - 8
02/16/2017 BUILDING - PROGRESS Partial Approval 1. STAIRWELL #3, NORTH EAST LANDING SLAB. OK TO POUR.
2. MASONRY PRE-GROUT - NORTH (COLORED) CMU WALL AT 48" AFFE. OK TO GROUT PROGRESS AREA.
02/14/2017 BUILDING - PROGRESS Partial Approval 1. BUILDING PRE-SLAB: FOOF SLAB AT GL: D - H/10.5 - 13.5. OK TO PLACE CONCRETE.
2. PLUMBING INTERMEDIATE: WASTE AND VENT LINES (2 1/2" - 4") AT GL: E/13 - 14.
3. MECHANICAL INTERMEDIATE: DUCT WORKS SECURED AND SEALED AT GL: D - H/16 - 19. OK TO INSULATE PROGRESS AREAS.
02/09/2017 BUILDING - PROGRESS Partial Approval PLUMBING INTERMEDIATE: WASTE & VENT LINES (2 1/2" - 4"). GL: F/15 - E/15.25
02/03/2017 BUILDING - PROGRESS Not ready for Inspection UPPER LEVEL CENTER SECTION OF ROOF RE-BAR INCOMPLETE. AT EDGE OF SLAB ON THE NORTH SIDE, THERE ARE BARS LAYING ON THE PLATFORM NEAR COLUMNS.
02/02/2017 BUILDING - PROGRESS Cancelled
02/01/2017 BUILDING - PROGRESS Partial Approval MECHANICAL ROUGH-IN IN AREA "B", GL: D - H/10 - 14. DUCT SYSTEM JOINTS SEALED. OK TO INSULATE PROGRESS AREAS.
01/30/2017 BUILDING - PROGRESS Partial Approval LEVEL #3 SLAB AT GL: 2 - 5/ C-G: OK TO PLACE CONCRETE.
01/27/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: D/17 - 18. NE STAIRWELL AREA. OK TO PLACE CONCRETE.
01/26/2017 BUILDING - PROGRESS Partial Approval COLUMNS AT GL: 8/C - G (5); 9/E - G (3); 10/G; STAIRWELL #2 ON LEVEL #3. STEM WALL FOOTING FOR NE STAIRWELL GL: D/ 17.5 - 18. OK TO PLACE CONCRETE AT PROGRESS AREAS.
01/25/2017 BUILDING - PROGRESS Not ready for Inspection STEM WALL AT NE CORNER - FOOTINGS NOT READY.
01/17/2017 BUILDING - PROGRESS Partial Approval COLUMNS (5) AT GL: 2/ C - G; 3/G; SE STAIRWELL AT GL: 2 - 2.5/E.5 - F.3. OK TO PLACE CONCRETE
01/16/2017 BUILDING - PROGRESS Not ready for Inspection COLUMNS AND STAIRS AT LEVEL 2 NEED TO BE WRAPPED.
01/11/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: C/5 - 6 AT 36". OK TO PLACE CONCRETE.
01/10/2017 BUILDING - PROGRESS Partial Approval STEM WALL REBAR - STEM WALL AT GL: A/1 - 3.5; 3.5/A - C. OK TO PLACE CONCRETE
01/04/2017 BUILDING - PROGRESS Partial Approval PRE-GROUT: CMU WALLS AT GL: D/18 - 18.5, CE/18 - 18.25; SE STAIRWELL. CMU WALLS AT GL: 1/AW - BW; AW/1 - 1.5 AT 48" - 72"/ OK TO GROUT PROGRESS AREAS.
12/27/2016 BUILDING - PROGRESS Partial Approval COLUMNS AT GL: 11/C - F; (4): 12/D - E (3); 13/C - F (4); 14/C - D (2); SHEAR WALL AT 14/D. FORMS SET - OK TO PLACE CONCRETE.
12/22/2016 BUILDING - PROGRESS Not ready for Inspection RAINED OUT
12/20/2016 BUILDING - PROGRESS Partial Approval MRCHANICAL ABOVE CEILING: DUCT SYSTEM FOR AREA "C"; OK TO SET FOR TESTING AND INSULATING
12/18/2016 BUILDING - PROGRESS Not ready for Inspection LEVEL 3; AREA SLAB #3; LEVEL 1, AREA #6 SOG
12/15/2016 BUILDING - PROGRESS Partial Approval COLUMNS: 18/E, F, G; 19/D - E; 17/E, F, G; H/18, 19; SHEAR WALL AT GL: D/ 17 - 18. OK TO PLACE CONCRETE AT PROGRESS AREAS.
12/13/2016 BUILDING - PROGRESS Not ready for Inspection NOT READY- COLUMNS AND SHEAR WALL
12/12/2016 BUILDING - PROGRESS Partial Approval LEVEL #3, COLUMNS AT GL: 17/C - D; D/17; E/16. COLUMNS FORMED - OK TO PLACE CONCRETE
12/01/2016 BUILDING - PROGRESS Partial Approval REBAR/COLUMNS: COLUMNS AT GL: C.25/4; C.25/5; SHEAR WALL AT GL: C/4 - 5. OK TO PLACE CONCRETE
11/30/2016 BUILDING - PROGRESS Prior to Final Inspectn
11/29/2016 BUILDING - PROGRESS Not ready for Inspection GRADE BEAMS NOT READY FOR INSPECTION
11/28/2016 BUILDING - PROGRESS Partial Approval VAULT AREA CAP SLAB AT GL: .5/C.5 - E.75; C.5/.5 - 2; 2/C.5 - E.75; E.75/.5 - 2. OK TO PACE CONCRETE IN PROGRESS AREAS.
11/21/2016 BUILDING - PROGRESS Partial Approval LEVEL3 AREA 1 FLOOR OK TO PLACE
11/18/2016 BUILDING - PROGRESS Cancelled CANCELED BY SCOTT
11/16/2016 BUILDING - PROGRESS Partial Approval LEVEL #2; COLUMNS AT GL: 7/D - G; 8/C, E, G; 9/D,F. OK TO SET FORMS AND PLACE CONCRETE.
11/15/2016 BUILDING - PROGRESS Not ready for Inspection LEVEL #3 SLAB
11/09/2016 BUILDING - PROGRESS Partial Approval EXCAVATION/ REBAR: BUILDING CURB FOOTINGS AT GL: G/8 - 9; D/5 - 6; DOWELING EPOXIED AT 12" O.C.
11/08/2016 BUILDING - PROGRESS Not ready for Inspection
11/07/2016 BUILDING - PROGRESS Partial Approval LEVEL #2SLAB AT GL: D - H/8 - 12; 9 - 10/ D - C, OK TO PLACE CONCRETE.
11/03/2016 BUILDING - PROGRESS Not ready for Inspection
11/01/2016 BUILDING - PROGRESS Partial Approval REBAR/LAYOUT: WALL AT GL: 14/E.5 -F.25; COLUMNS AT GL: G/13, G/14, 15/ D, E, F; 11/D,E, F. COLUMNS FORMED - OK TO PROGRESS AREAS.
10/31/2016 BUILDING - PROGRESS Not ready for Inspection
10/31/2016 BUILDING - PROGRESS Not ready for Inspection
10/30/2016 BUILDING - PROGRESS Not ready for Inspection
10/25/2016 BUILDING - PROGRESS Partial Approval GRADE BEAM AT GL: A/ 9.3 - 10.3; INTERIOR PEDISTALS AT GL: A/9.3, A/10.3, C/9, B/9, C/10.3 OK TO PLACE CONCRETE
10/19/2016 BUILDING - PROGRESS Partial Approval EXCAVATION/ LAYOUT REBAR: GRADE BEAM AT GL: C/3-4. OK TO PLACE CONCRETE.
10/17/2016 BUILDING - PROGRESS Partial Approval GRADE BEAM AT GL: G/ 4 - 5. OK TO POUR PROGRESS AREA.
10/10/2016 BUILDING - PROGRESS Partial Approval REBAR PLACEMENT OF 2ND LEVEL SLAB COLUMNS AT GL: 19/B - C; 18/F, G, H; 17/ E, G, H. OK TO SET FORMS AND POUR COLUMNS.
10/06/2016 BUILDING - PROGRESS Partial Approval 2ND LEVEL SLAB AT GL: D - H/16.5 - 20; ENTRY FOUNDATION GRADE BEAMS AT GL: A - C/ 9 - 10.5. OK TO PLACE CONCRETE AT PROGRESS AREAS.
10/06/2016 BUILDING - PROGRESS Not ready for Inspection
09/30/2016 BUILDING - PROGRESS Partial Approval SLAB ON GRADE AT GL: D -H/8 - 11. OK TO PLACE CONCRETE.
09/26/2016 BUILDING - PROGRESS Not ready for Inspection
08/22/2016 BUILDING - PROGRESS Partial Approval INFORMATION ONLY