Permit: T16CM03514

Parcel: 11202003D

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
04/11/2019 BUILDING PRE-SLAB Approved
03/06/2018 BUILDING PRE-SLAB Partial Approval INTERIOR SLAB AT LEVEL #1; GL: D-E/19-20. OK TO PLACE CONCRETE
08/18/2017 BUILDING PRE-SLAB Partial Approval DEPRESSED MRI PAD AT GL: D/18 - 19. OK TO PLACE CONCRETE.
08/14/2017 BUILDING PRE-SLAB Partial Approval LEVEL #1, AREA #4; REBAR IN PLACE, REMOVE RAIN WATER; GENERAL CLEAN-UP. OK TO PLACE CONCRETE.
07/27/2017 BUILDING PRE-SLAB Partial Approval WALKING BRIDGE PAD (SOUTH); EMBEDS ARE IN PLACE AS PER PLANS. OK TO PLACE CONCRETE.
02/06/2017 BUILDING PRE-SLAB Partial Approval SLAB ON LEVEL #4, GL: D/12 - 16; 12/D - 12. OK TO PLACE CONCRETE
01/26/2017 BUILDING PRE-SLAB Partial Approval VAULTS (4) SLURRY PLACED THROUGHOUT FOR EQUIPMENT PADS.
01/19/2017 BUILDING PRE-SLAB Partial Approval EQUIPMENT IN 4 VAULTS - OK TO PLACE CONCRETE.
12/19/2016 BUILDING PRE-SLAB Partial Approval SLAB ON GRADE: AREA 6; GL: A/2 -4, 4/A - G, G/2 - 4, 2/A - G. OK TO PLACE CONCRETE WHEN REBAR IS IN PLACE - REMOVE WATER IN LOW LYING AREAS.
12/11/2016 BUILDING PRE-SLAB Partial Approval LANEX TOP-OUT SLAB AT GL: A - C/.5 - 3.5. OK TO PLACE CONCRETE.
12/01/2016 BUILDING PRE-SLAB Partial Approval LEVEL #3; GL: 13.5 - 16.5/D - H; OK TO PLACE CONCRETE UPON FINAL SPECIAL INSPECTION.
11/22/2016 BUILDING PRE-SLAB Partial Approval MAIN ENTRY SLAB AREA AT GL: 9 - 10.75/ B - H. OK TO PLACE CONCRETE
10/27/2016 BUILDING PRE-SLAB Partial Approval LEVEL #2 GL: D - H/ 4 - 1 OK TO PLACE CONCRETE AFTER 6" CUT BACK ON NORTH EXTERIOR WALL HAS BEEN PROPERLY INSTALLED.
10/19/2016 BUILDING PRE-SLAB Partial Approval LEVEL #2 SLAB AT GL: D - H/ 13.5 - 16; OK TO PLACE CONCRETE IN PROGRESS AREA.
10/19/2016 BUILDING PRE-SLAB Partial Approval LEVEL #1" SLAB AT GL: C - G/ 4 - 8. OK TO PLACE CONCRETE AT PROGRESS AREA.