Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T16CM03513

Parcel: 11202003D


Addresses:

3838 N CAMPBELL AV


Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Permit Number - T16CM03513

Inspection Description - BUILDING - PROGRESS

Inspection Status - Approved

Date Description Inspector Results Comments
09/22/2017 BUILDING - PROGRESS Approved
08/11/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT, PARKING STRUCTURE LEVEL#1: 6 CRASH WALLS AT 32"; CMU WALLS OK TO GROUT.
07/26/2017 BUILDING - PROGRESS Partial Approval SHEET ROCK NAILING: (EXTERIOR) ELEVATOR AREA (EAST AND WEST WALLS) OK TO WATERPROOF AND COVER.
07/05/2017 BUILDING - PROGRESS Partial Approval FRAMING - ELECTRIC CLOSETS (PANELS AND DISCONNECTS) A LEVELS 2 - 3 FOR ELEVATORS (SOUTH STAIRWELL). OK TO INSULATE AND COVER WALLS.
06/28/2017 BUILDING - PROGRESS Partial Approval PLUMBING ROOM DRAINS - ELEVATOR AREA AT LEVELS 3 - 1; PRIMARY AND OVER-FLOW LINES - UNDER TEST.
06/23/2017 BUILDING - PROGRESS Partial Approval ELECTRIC LUNDERGROUND; 2 CONDUITS @ 3/4" - SOUTH SIDE OF PARKING STRUCTURE AT GL: DW - DE/7. OK TO COVER PROGRESS AREA..
ELECTRIC INTERMEDIATE: ELECTRIC ROOM AT GL: DE/17, TRANSFORMER #LS101 - OK TO ENERGIZE
06/07/2017 BUILDING - PROGRESS Partial Approval MIDDLE STAIRWELL - LANDINGS AND STEPT. OK TO PLACE CONCRETE.
03/22/2017 BUILDING - PROGRESS Not ready for Inspection MASONRY PRE-GROUT AT STORAGE ROOMS (48" - 96")
03/21/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT - CMU WALLS AT 0" - 48" GL: 10/BE - CE, CE/10 - 11. OK TO GROUT PROGRESS AREA. ELECTRIC CONSTRUCTION POWER LINES FROM CANCER CENTER TO PARKING STRUCTURE ELECTRIC ROOM (PANEL) - TO PANELS AT MEDICAL CENTER LEVELS 1, 2, 3: (PT1, PT2-A, PT3-B). OK TO ENERGIZE FOR TEMPORARY CONSTRUCTION POWER.
03/13/2017 BUILDING - PROGRESS Partial Approval ELECTRIC INTERMEDIATE: TEMP POWER SYSTEM FED FROM PARKING STRUCTURE TO MEDICAL STRUCTURE; PANESL, TRANSFORMER; DISCONNECTS IN PLACE - SYSTEM TO BE COMPLETE BY 15 MARCH.
02/28/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: ELEVATOR AREA (COLORED WALL) AT 40' - OK TO GROUT PROGRESS AREA.
02/27/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT - ELEVATOR WALLS AT 37'; STORAGE ROOM EAST WALL AT 48". OK TO GROUT PROGRESS AREAS.
02/22/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: ELEVATOR AREA CMU WALLS AT 35' OK TO GROUT PROGRESS AREA.
02/21/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-ROUT AT GL: 11/BE - CE, AT 4' 8" AFFE. OK TO PLACE GROUT.
02/15/2017 BUILDING - PROGRESS Partial Approval LEVEL #1, SLAB AT GL: 17 - 18/AE - DE. OK TO PLACE CONCRETE.
02/13/2017 BUILDING - PROGRESS Not ready for Inspection PLUMBING ROOF DRAINS AND OVER - FLOW DRAINS (SOUTH SIDE): NOT READY, WILL RESCHEDULE FOR 14 FEB
02/09/2017 BUILDING - PROGRESS Partial Approval RAMP SLAB AT GL: 14 - 18/BE - CE. OK TO PLACE CONCRETE.
02/08/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL 2 RAMP (SOUTH HALF) TO LEVEL 1 AT GL: BE.5 - CE/9 - 18. OK TO PLACE CONCRETE.
02/08/2017 BUILDING - PROGRESS Partial Approval LEVEL #1, SLAB AT GL: CE - DE/9 -17. OK TO PLACE CONCRETE.
02/06/2017 BUILDING - PROGRESS Partial Approval SLAB ON GRADE AT GL: 9 - 18/AE, AE - BE/9, 9 - 18/BE - BW; AE - BE/18. OK TO PLACE CONCRETE.
02/03/2017 BUILDING - PROGRESS Not ready for Inspection
01/31/2017 BUILDING - PROGRESS Partial Approval LEVEL #2 SLAB AT GL: 9/CW - DW; DW/9 - 18. OK TO PLACE CONCRETE.
01/30/2017 BUILDING - PROGRESS Partial Approval SLAB AT LEVEL #2, GL: 9 - 11/BW.T - CW. OK TO PLACE CONCRETE.
01/27/2017 BUILDING - PROGRESS Partial Approval SUPPORT ROOM SLABS #1002, 1003, 1005, 1006 - OK TO PLACE WHEN DOWELS AND CHAIRS ARE IN PLACE.
01/23/2017 BUILDING - PROGRESS Partial Approval LEVEL #2; SLAB AT GL: CE - BE/11 - 18. OK TO PLACE CONCRETE
01/20/2017 BUILDING - PROGRESS Not ready for Inspection MASONRY PRE-GROUT: STAIRWELLS AND ELEVATOR
01/19/2017 BUILDING - PROGRESS Partial Approval SLABS FOR ELECTRIC/MECHANICAL ROOMS #1002, 1003 (PARTIAL), 1005, 1006: OK TO PLACE CONCRETE, MASONRY GROUT AT SW AND SE STAIRWELLS, CMU WALLS AT 8' TO 12'. OK TO GROUT ROGRESS AREAS.
01/18/2017 BUILDING - PROGRESS Partial Approval RAMP SLAB AT LEVEL 3 - 2.5: GL: BE/5 - CE/9 - 17. OK TO PLACE CONCRETE
01/16/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: SE & SW STAIRWELLS AT 8' TO 12'. OK TO GROUT. ELEVATOR WALL (COLORED) AT 7' 4" - OK TO GROUT.
01/12/2017 BUILDING - PROGRESS Prior to Final Inspectn MASONRY PRE-GROUT AT ELEVATOR AND SE & SW STAIRWELLS....NOT READY TO GROUT.
01/11/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT; ELEVATOR CMU WALLS AT 48" AFFE AT GL: DW/7 -8. OK TO GROUT. EXCAVATION LAYOUT/REBAR: ELECTRIC ROOM FOOTINGS AT GL: 8/BE -CE. VERTICAL BARS ARE SHORT; WILL NEED TO ADD-ON LENGTH AT STEM WALL. OK TO PLACE CONCRETE. (RFI #43R-2)
01/10/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: SW STAIR WELL AT 8'; GL: DW/.5 - 1; CW.9/.5 -1. OK TO GROUT.
01/09/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #3: SLABS #2 AND #5: GL: CE/14 - 18, AE.5/14 - 18. OK TO PLACE CONCRETE.
01/08/2017 BUILDING - PROGRESS Partial Approval
01/08/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE GROUT: SOUTH ELEVATOR WALL AT GL: DE.5/6.75 - 8.25 AT 48". OK TO GROUT. *NOTE: CMU WALL AT GL: DW/6.8 - 7.5 ( IS THE WALL DESIGNATED A CRASHWALL?)
01/05/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: S.W. STAIRWELL, CMU WALLS AT GL: CW.7/.5 - 1, DW/.5 - 1. OK TO GROUT PROGRESS AREAS. PRE-SLAB: LEVEL #2, SLABS #2 AND #5. OK TO PLACE CONCRETE.
01/04/2017 BUILDING - PROGRESS Partial Approval PRE-SLAB AT GL: 2 - 4.5/A - G, (LEVEL #2, AREA 6); STAIRWELL #4, COLUMNS 10.3D, 11D, E, F, G, G/11.5, 13/H, E/12, F/12. OK TO PLACE CONCRETE IN PROGRESS AREAS.
12/28/2016 BUILDING - PROGRESS Not ready for Inspection ELECTRIC NOT READY FOR INSPECTION
12/27/2016 BUILDING - PROGRESS Partial Approval NOT READY: LEVEL #1, SLAB #3.
12/22/2016 BUILDING - PROGRESS Not ready for Inspection RAINED OUT
12/21/2016 BUILDING - PROGRESS Not ready for Inspection LEVEL #1, SLAB ON GRADE #3, NOT READY.
12/20/2016 BUILDING - PROGRESS Partial Approval NOT READY - LEVEL #1; SLAB ON GRADE #3.
12/18/2016 BUILDING - PROGRESS Partial Approval RAMP WALL (DOWN), LEVEL # 1.5; GL: 15/AE - DE; 2 COLULUMN FOOTINGS (F6) AT GL: 18/CE.75 - DE. OK TO PLACE CONCRETE IN PROGRESS AREAS.
12/15/2016 BUILDING - PROGRESS Not ready for Inspection LEVEL #3: SLABS 2 & 4 INCOMPLETE
12/14/2016 BUILDING - PROGRESS Partial Approval 1. PLUMBING ROUGH SOIL: DRAIN LINES OF 4" CLEAN-OUTS; 6" - 12" DRAIN LINES AT GL: 16 - 17/ AE - DE. OK TO COVER PROGRESS AREAS. 2. EXCAVATION LAYOUT/REBAR: SOUTH STAIRWELL FOOTINGS AT GL: 18/CE.5 - DE. OK TO PLACE CONCRETE. 3. BUILDING PRE-SLAB: LEVEL #1: SLAB #1 (SOG), GL: 3.25 - 6.25/ AW - DW. OK TO PLACE PROGRESS AREAS.
12/13/2016 BUILDING - PROGRESS Partial Approval LEVEL #3: SLAB #4 GL: BW - BW.5/ 1 - 8; SLAB #6 GL: AW - AW.5/ 1 - 8; SLAB #3 GL; CW - BW.5/ 8 OK TO PLACE CONCRETE AR PROGRESS AREAS.
12/11/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING - 12" DRAIN LINES
12/08/2016 BUILDING - PROGRESS Not ready for Inspection LEVEL #1 , SLAB #2
12/07/2016 BUILDING - PROGRESS Cancelled
12/06/2016 BUILDING - PROGRESS Partial Approval ELECTRIC UNDERGROUND - ROOMS #101, 102, 103 (ELECTRIC ROOMS) CONDUITS IN PLACE: 4 @ 4", 1 @ 3", 3 @ 2" 4 @ 1 1/2" , 2 @ 1". BUILDING PRE-SLAB: LEVEL #3 GL: SECTION #1 CW.75 - DW/ 1 - 8; SECTION #3: BW.75 - CW/ 1 - 8. LEVEL #1 GL: 1 - 3.25/ AW - DW. ENSURE CHAIRS AND REBAR IS PROBERLY PLACED. OK TO POUR PROGRESS AREAS.
12/04/2016 BUILDING - PROGRESS Not ready for Inspection NOT READY SEE PLUMBING REVISIONS
12/01/2016 BUILDING - PROGRESS Partial Approval EXCAVAION/LAYOUR REBAR: ELECTRIC ROOM PAD (#4 REBAR AND #4 WIRE MESH) AT GL: AW/1 - 1.25; 1/AW - AW.25. OK TO POUR PROGRESS AREA.
11/30/2016 BUILDING - PROGRESS Partial Approval ELECTRIC UNDERGROUND: 2 EACH 2 1/2" CONDUIT LINES AT GL: BE.5/15 - 18. OK TO COVER PROGRESS AREA.
11/29/2016 BUILDING - PROGRESS Partial Approval ELECTRIC UNDERGROUND (ELECTRIC ROOM AT LEVEL #1); CONDUITS AT 10 EACH 3"; 2 AT 4"; 7 AT 1"; 4 AT 2". GL: AW/1 - 1.25, 1/AW - AW.25. OK TO COVER CONDUITS.
11/28/2016 BUILDING - PROGRESS Partial Approval PLUMBING UNDERGROUND - 6" DRAIN LINE AT GL: CW - CE/6 - 7.8. OK TO COVER AREA. ELECTRIC UNDERGROUND: ELECTRIC ROOM - CONDUITS (20) - 3/4" - 4", DATA/POWER LINES AT GL: CE/3.75 (5 EACH 1 1/2", 3 EACH 2", 1 EACH 3", 2 EACH 4" DATA LINES. OK TO COVER PROGRESS AREAS.
11/24/2016 BUILDING - PROGRESS Partial Approval PLUMBING UNDERGOUND : 4" DRAIN LINE AT ELEVATOR PIT: GL: 6.8 - 8/W; DW - CW/7. OK TO COVER PROGRESS AREAS.
11/22/2016 BUILDING - PROGRESS Not ready for Inspection 6" STORM DRAIN LINE AT GL: CE/12 - 14. NEEDS TO BE UNDER TEST.
11/21/2016 BUILDING - PROGRESS Not ready for Inspection
11/18/2016 BUILDING - PROGRESS Partial Approval OK TO COVER STORM DRAINS.
11/17/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING - 8" - 10" LINES ARE NOT UNDER TEST. INSPECTION CANCELLED BY BEL-AIRE (MIKE)
11/16/2016 BUILDING - PROGRESS Not ready for Inspection ELECTRIC AND PLUMBING (PLUMBING LINES NOT UNDER TEST)
11/15/2016 BUILDING - PROGRESS Not ready for Inspection ELECTRIC AND PLUMBING
11/09/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING AND ELECTRIC
11/08/2016 BUILDING - PROGRESS Not ready for Inspection ELECTRIC AND PLUMBING - NOT READY
11/08/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING UNDER GROUND NOT READY.
11/06/2016 BUILDING - PROGRESS Partial Approval STORM DRAINS AT GL: BW/5 - 7 (6"), CW/5 - 7 (6"); 6.5/ AW.25 - DW .25 (4" - 8"); DW.25/ 6.75 - 6.8 (6"); CW/6 - 6.5 (6"); AW.8/5 - 6.5 (6"). OK TO COVER PROGRESS AREAS.
11/03/2016 BUILDING - PROGRESS Not ready for Inspection
11/02/2016 BUILDING - PROGRESS Partial Approval ELEVATOR PIT CMU WALLS AT 0" - 56" - OK TO GROUT PROGRESS AREAS (ALL CELLS TO BE GROUTED)
11/01/2016 BUILDING - PROGRESS Not ready for Inspection PLUMBING NOT READY
10/07/2016 BUILDING - PROGRESS Partial Approval SPECIAL INSPECTION SCHEDULE FOR WELDS AND DRY-PACKING.