Inspection Status: Approved
Inspection History: ZONING PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 03/01/2021 |
ZONING PROGRESS |
|
Approved |
ZONING FINAL APPROVED. ALL FIELD INSPECTIONS MATCH APPROVED LANDSCAPE, HARDSCAPE, RENDERINGS AND ELEVATIONS. |
| 11/05/2020 |
ZONING PROGRESS |
|
Partial Approval |
FIELD INSPECTION: CONDUCTED FULL INSPECTION, OPENINGS, ARCHTECTURAL, RENDERINGS AND MATERIALS. FYI, AFTER SPEAKING WITH BUILDING, OWNERS MAY BE LOOKING TO FINAL OUT PERMIT. HAVE PROVIDED A FULL REPORT AND PRESENTATION SHOWING PLANNERS COMPLIANCE. NEXT STEP: WILL MEET WITH MARIA AND NICK TO DISCUSS MY REPORT AND SEE IF FINAL IS APPROPRIATE. |
| 07/28/2020 |
ZONING PROGRESS |
|
Partial Approval |
ON SITE PROGRESS INSPECTION COMPLETED. REPORT TO BE GENERATED AND SENT TO SPECIAL DISTRICTS PLANNERS ON 07/29/20 FOR REVIEW AND COMMENT. NEXT STEP: MEET WITH PLANNERS TO DISCUSS COMPLIANCE. AFTER WILL COMMUNICATE WITH REPRESENTATIVES OF FINDINGS. |
| 04/29/2019 |
ZONING PROGRESS |
|
Prior to Intermediates |
Design Review must be completed prior to approval of this inspection |