Permit: T16CM02856

Parcel: 12404100A


Addresses:

930 E 2ND ST

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
05/20/2020 MECHANICAL - INTERMEDIATE Approved
04/21/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #10; Rooms 1030; 1031; 1032; 1033; 1034; 1036. Duct system and thermostat lines are in place.
04/16/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #9; Rooms #931; 932; 933; 934; 936. Duct system and thermostat landed in place.
04/06/2020 MECHANICAL - INTERMEDIATE Partial Approval RVI-Outside air shafts at Levels 9-14; duct system in place. Level #7; duct system in rooms: 730; 731; 732; 733; 734; 736.
04/02/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #7; all room units and fitness area. Ok to insulate and cover walls in room units.
03/20/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/19/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #4; in wall duct system and thermostat lines.
03/17/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/13/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/12/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #11; Rooms: 1100; 1101; 1103; 1105; 1107; 1109; duct system in place, thermostat locations.
03/11/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Canceled by contractor.
03/10/2020 MECHANICAL - INTERMEDIATE Partial Approval Level#11; Rooms: 1109; 1110; 1111; 1112; duct systems are in place, thermostat locations set.
03/05/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/04/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/03/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #10; duct system and thermostats in rooms: 1000; 1001; 1003; 1005; 1007; 1009; 1010; 1011; 1012.
02/26/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #9; electric in walls, Rooms: 900; 901; 902; 903; 904; 905; 907; 910; 911; 912. Ok to cover walls.
02/25/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #6; Rooms: 618; 619.
02/24/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/21/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection
02/20/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled
02/19/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #8; Rooms: 800; 802; 864.
02/14/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Fire stopping above lid not complete.
02/13/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #7; Room 710; duct system above ceiling and in walls.
02/12/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/11/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #7; Rooms: 700; 701; 702; 703. Duct system in walls and ceiling.
02/10/2020 MECHANICAL - INTERMEDIATE Partial Approval Level#7; Rooms 707; 709; 711; 712.
02/07/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled
02/06/2020 MECHANICAL - INTERMEDIATE Partial Approval Mechanical in walls and above ceilings (Flex duct system).
02/05/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #6; in wall and above ceiling duct systems in rooms: 607; 609; 610; 611; 612; 613
02/04/2020 MECHANICAL - INTERMEDIATE Partial Approval Mechanical duct systems in walls and above ceiling.
01/31/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/30/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/27/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #5; Rooms: 503; 505; 507.
01/25/2020 MECHANICAL - INTERMEDIATE Partial Approval Units 511 and 513 electrical and mechanical OK. Unit 510 mechanical still needs attention.Electrical in 510 approved.
01/23/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #5, Rooms 509; 512.
01/22/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection CONTACTOR CANCELED
01/17/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #5; Rooms: 517; 519; 520; 521; 522. Level #4; Room 418.
01/15/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #3; Room 344.
01/14/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #3; Room 318
01/13/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/10/2020 MECHANICAL - INTERMEDIATE Partial Approval (Mechanical above ceiling); corridor #360. Ensure all corridor penetrations are properly fire caulked.
01/09/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #4; Rooms: 400; 401; 402; 403; 405; 409; 430; 434. Ok to cover walls.
01/07/2020 MECHANICAL - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/06/2020 MECHANICAL - INTERMEDIATE Partial Approval Level #2; Corridors: 266; 319. Level #3: 312; Level #4; Rooms: 411; 412; 413; 415; 417; 420
01/02/2020 MECHANICAL - INTERMEDIATE Partial Approval Hydronic 2" lines; in Mechanical rooms of units at Levels 4 through 6. Ok to insulate lines.
12/30/2019 MECHANICAL - INTERMEDIATE Partial Approval Garage Level#1; Hydronic Lines (4"-6"); Zones 1-3; Zone #1; tested up to level #4: Zones 2 & 3 tested up to level #4 (6" lines). All lines tested at 125 psi. Level #4; Rooms 419; 421; 422
12/19/2019 MECHANICAL - INTERMEDIATE Partial Approval Level#3; Room 351. Level #4; Rooms 463; 464.
12/18/2019 MECHANICAL - INTERMEDIATE Partial Approval Duct systems in rooms 348; 350; 354.
12/17/2019 MECHANICAL - INTERMEDIATE Cancelled Contractor cancelled, reschedule for 18 December.
12/13/2019 MECHANICAL - INTERMEDIATE Partial Approval Level #3; Room 309. Ok to insulate and cover walls.
12/10/2019 MECHANICAL - INTERMEDIATE Partial Approval Level #3; Rooms: 300; 301; 303; 305; 307; 311; 313; 340; 342