Permit: T16CM02856

Parcel: 12404100A


Addresses:

930 E 2ND ST

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Date Description Inspector Results Comments
11/17/2020 ELECTRIC - INTERMEDIATE Approved 2090
04/30/2020 ELECTRIC - INTERMEDIATE Partial Approval Partial. Level #1; Service disconnect #SES 1 and service disconnect #SES 2. Ok to energize service panels.
04/28/2020 ELECTRIC - INTERMEDIATE Partial Approval Partial. Meter sets for the following rooms: Level #3: 300; 301; 303; 305; 307; 309; 310; 311; 312; 313; 315; 317; 318; 319; 321; 322; 342; 344; 346; 348; 349; 350; 351; 354.

Level #4: 400; 401; 402; 403; 404; 405; 407; 409; 410; 411; 412; 413; 415; 417; 418; 419; 420; 422; 430; 431; 432; 433; 434; 436

Level #5: 500; 501; 502; 503; 504; 505; 507; 509; 510; 511; 512; 513; 515; 517; 518; 519; 520; 521; 522; 530; 531; 532; 533; 534; 536.

Level #6: 600; 601; 602; 603; 604; 605; 607; 609; 610; 611; 612; 613; 615; 617; 618; 619; 620; 621; 622.

Level #7: 700; 701; 702; 703; 704; 705; 707; 709; 710; 711; 712; 730; 731; 732; 733; 734; 736
04/21/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #10; in wall electric in rooms 1030; 1031; 1032; 1033; 1034; 1036. Ok to cover walls.
04/21/2020 ELECTRIC - INTERMEDIATE Partial Approval level #2 Meter set. Meters #200; 201; 203; 240; 242; 246; 252; 255; 2 house panels. Ok to set unit meters.
04/16/2020 ELECTRIC - INTERMEDIATE Partial Approval RVI Level #9; in wall electric in rooms 931; 932; 933; 934; 936. Ok to insulate and cover walls.
04/16/2020 ELECTRIC - INTERMEDIATE Partial Approval RVI Garage area electric room; meters to be set in switch gear # DPR Residential SES; DPH Hotel SES. Clear to set meters.
04/06/2020 ELECTRIC - INTERMEDIATE Partial Approval RVI-In wall electric in rooms: 730; 731; 732; 733; 734; 736. Ok to cover walls.
04/02/2020 ELECTRIC - INTERMEDIATE Approved #7; all room units and fitness area.
03/20/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/19/2020 ELECTRIC - INTERMEDIATE Partial Approval Partial. Level,#4; in wall electric in rooms: 430; 431; 432; 433; 434; 436. Ok to cover walls.
03/17/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/13/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/12/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #11; Rooms: 1100; 1101; 1103; 1105; 1107; 1109; Electric in walls. Ok to cover walls.
03/11/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Canceled by contractor.
03/05/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/04/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
03/03/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #10; in wall electric in rooms: 1000; 1001; 1003; 1005; 1007; 1009; 1010; 1011; 1012. Ok to cover walls.
02/26/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #9; electric in walls, Rooms: 900; 901; 902; 903; 904; 905; 907; 910; 911; 912. Ok to cover walls.
02/25/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #3; Rooms: 344; 348; 350; 354. Level #6; Rooms: 618; 619. (Electric in walls). Ok to cover walls.
02/24/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/21/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection
02/20/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled
02/19/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #8; Rooms: 800; 802; 864.
02/14/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Fire stopping above lid not complete.
02/13/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #7; Room #710. Ok to insulate and cover walls.
02/12/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
02/11/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #7; Rooms: 700; 701; 702; 703. Ok to insulate and cover walls.
02/10/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #7; Rooms 711; 712; 709; 707. Ok to insulate and cover walls.
02/07/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled
02/06/2020 ELECTRIC - INTERMEDIATE Partial Approval Electric in walls at Level #6; Rooms: 600; 601; 602; 603; 605. Ok to insulate and cover walls.
02/05/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #6; in wall electric in rooms: 607; 609; 610; 611; 612; 613. Ok to insulate and cover walls.
02/04/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #6; I wall electric in rooms: 617; 619; 620; 621; 622. Ok to insulate and cover walls.
01/31/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled
01/30/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/27/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #5; in wall electric in Rooms: 503; 505; 507. Ok to cover walls.
01/23/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #5; Rooms 509; 512. In wall electric
01/22/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection CONTARCTOR CANCELED
01/15/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #3; Room 344.
01/14/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #3; Room 318
01/13/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/10/2020 ELECTRIC - INTERMEDIATE Partial Approval (Electric above ceiling); corridor #360
01/09/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #4; Rooms 401; 402; 403; 405; 409; 430; 434; 400. Ok to cover walls.
01/07/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
01/06/2020 ELECTRIC - INTERMEDIATE Partial Approval Level #2; Corridors: 266; 319. Level #3: 312; Level #4; Rooms: 411; 412; 413; 415; 417; 420
01/02/2020 ELECTRIC - INTERMEDIATE Not ready for Inspection Contractor cancelled.
12/30/2019 ELECTRIC - INTERMEDIATE Partial Approval Level #4; Rooms 419; 421; 422.
12/19/2019 ELECTRIC - INTERMEDIATE Partial Approval Level#3; Room 351. Level #4; Rooms 463; 464. Ok to cover walls.
12/18/2019 ELECTRIC - INTERMEDIATE Partial Approval Electric in walls in rooms 350; 354; 348.
12/17/2019 ELECTRIC - INTERMEDIATE Cancelled Contractor cancelled, reschedule for 18 December.
12/13/2019 ELECTRIC - INTERMEDIATE Partial Approval Room #309 on Level #3.