Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 05/20/2020 |
BUILDING ABOVE CEILING |
|
Approved |
|
| 04/28/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #7 (Burn Area Corridor). Ok to cover ceiling. |
| 04/28/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #7 (Burn Area Corridor). Ok to cover ceiling. |
| 04/24/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
No contact information to schedule inspection. |
| 04/22/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RVI Level #7 (Burn area rooms). 01044; rooms 730; 731; 732; 733; 734; 736. |
| 04/21/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 04/16/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RVI Level #9; (Burn Area). Corridor. Penetrations Fire caulked. |
| 04/14/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
RVI Contractor cancelled. |
| 04/09/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
RVI Contractor cancelled. |
| 04/08/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RVI Level #12 Corridor ceiling. 01044 Fire caulking. |
| 04/06/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
RVI-Contractor cancelled. |
| 03/12/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Level #8; Corridor #860. Ok to cover progress area. |
| 03/11/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Canceled by contractor. |
| 01/02/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 12/30/2019 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Mechanical, Electrical, Plumbing above ceiling in corridor #260 South. Insure all penetrations are properly fire caulked. |
| 12/27/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
|
| 12/12/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 12/10/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 12/09/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled |
| 12/05/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled |
| 12/04/2019 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Level #4; Rooms: 407; 409; 411; 412; waste and vent lines |
| 12/03/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 12/02/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |
| 11/21/2019 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Contractor cancelled. |