Permit: T16CM02856

Parcel: 12404100A


Addresses:

930 E 2ND ST


Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T16CM02856

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
05/20/2020 FRAMING Approved
04/09/2020 FRAMING Partial Approval RVI Stairwell #2; Levels #2-#14; hand rail backing in place. Ok to insulate and cover walls.
04/08/2020 FRAMING Partial Approval RVI Stairwell #1; Levels: Garage through Level #15. Ok to insulate and cover the walls.
04/06/2020 FRAMING Partial Approval RVI-Trash chutes at Levels 1-7
04/02/2020 FRAMING Approved #7; all room units and fitness area.
03/20/2020 FRAMING Partial Approval Level #15, Hotel bar roof parapets at GL: 3.4/D-E.6; E.6-F.5/2.2; 2.2-4/F.5; 7.8/A-B, A/7.8-9.8; 9.8/A-C. Ok to cover walls.
03/19/2020 FRAMING Not ready for Inspection Contractor cancelled.
03/18/2020 FRAMING Partial Approval Level #12; Rooms #1200; 1201.
03/17/2020 FRAMING Partial Approval Level #6; Rooms: 630; 631; 632; 633; 634; 636. Exterior wall framing at GL: 12/A-D.3; D.3/12-9; 9/D.3-H; H/9-7.1.
03/13/2020 FRAMING Partial Approval Level #15 parapet walls; Northwest parapet walls at 6’7"; East side center portion of parapet wall at 10’2". Ok to cover progress areas.
03/12/2020 FRAMING Not ready for Inspection Contractor cancelled.
03/11/2020 FRAMING Not ready for Inspection Canceled by contractor.
03/10/2020 FRAMING Partial Approval Level 15; Roof Terrace at GL: 3.4/D-E.9; E.9/3.4-3.2; 3.2/E.9-F.5; F.5/3.2-4; G/4-1.8; 1.8/G-E.5; E.5/1.8-3. 01036. Not ready. Contractor cancelled
03/09/2020 FRAMING Not ready for Inspection Contractor cancelled.
03/06/2020 FRAMING Partial Approval Level #5; Interior and exterior framing: 504; 530; 531; 532; 533; 534; 536. Level #12; Interior framing, Rooms: 1211; 1230; 1231; 1232; 1233; 1236.
NOTE: At approximately 1000 hours, a tool gang box from CECO Concrete fell from level #14; Southwest area. The box impacted in the street between The Collective and the Marriott Hotel. No injuries were sustained and the proper authorities were notified. The box was removed and work in the area continued. Cause of the falling box is unknown to this Inspector at thIs time,
03/05/2020 FRAMING Partial Approval Level #15 High Roof, Elevator Lobby: East, North, West walls.
North Elevator shaft framing from Basement level to Level #15. Ok to fire caulk shafts.
03/04/2020 FRAMING Partial Approval Level #12; unit framing at Rooms: 1203; 1205; 1207; 1209; 1210; 1212.
03/03/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/28/2020 FRAMING Partial Approval Level #4; Rooms: 431; 434; 436.
02/27/2020 FRAMING Partial Approval Level #4, Rooms: 430; 432; 433.
02/26/2020 FRAMING Not ready for Inspection Contractor cancelled
02/25/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/24/2020 FRAMING Partial Approval Level #11; Rooms: 1100; 1101; 1102; 1103; 1105; 1107; 1109; 1110; 1112; 1163; 1164.
02/21/2020 FRAMING Partial Approval Stairwell frame in units 344, 348, 350, 354 ok
02/20/2020 FRAMING Partial Approval Level #15; Elevator Lobby exterior walls and roof; Room #1581; North, South and West walls; West portion of roof.
02/19/2020 FRAMING Not ready for Inspection Contractor cancelled
02/14/2020 FRAMING Not ready for Inspection Canceled
02/13/2020 FRAMING Partial Approval Level #10; Room #1010.
02/12/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/11/2020 FRAMING Partial Approval Level #10; Rooms: 1000; 1001; 1002; 1003; 1005; 1007.
02/10/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/07/2020 FRAMING Not ready for Inspection Contractor cancelled
02/06/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/05/2020 FRAMING Not ready for Inspection Contractor cancelled.
02/04/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/31/2020 FRAMING Partial Approval Level #9; Rooms: 900; 901; 902; 903; 904; 905; 907; 909; 910; 911; 912; 965.
01/30/2020 FRAMING Partial Approval Level #1; 3 each columns at GL: H/8.8; H/7.9; H/7.1. Ok to cover progress areas.
01/27/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/26/2020 FRAMING Partial Approval Units 511 and 513 electrical and mechanical OK. Unit 510 mechanical still needs attention.Electrical in 510 approved.
01/24/2020 FRAMING Partial Approval Level #8; Rooms: 800; 801; 802; 803; 804; 807; 809; 810; 811; 812; 805.
01/23/2020 FRAMING Partial Approval Level #5; Rooms 509; 512. In wall electric
01/22/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/17/2020 FRAMING Not ready for Inspection
01/16/2020 FRAMING Not ready for Inspection Per super
01/15/2020 FRAMING Partial Approval Level #6; Rooms: 600; 601; 602; 603; 604; 605; 607; 610; 612.
01/14/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/13/2020 FRAMING Partial Approval Level #6; Rooms, 613; 615; 617; 618. Level #7; Corridor #760; 763; 764.
01/10/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/09/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/07/2020 FRAMING Partial Approval Level #6; Rooms: 609; 630; 632; 634.
01/06/2020 FRAMING Not ready for Inspection Rescheduled for 7 January.
12/31/2019 FRAMING Partial Approval Level#6; Rooms: 611; 620; 621; 622.
12/24/2019 FRAMING Not ready for Inspection Contractor cancelled. Crew sent home due to rain.
12/20/2019 FRAMING Partial Approval Level#5; Rooms 510; 512; Level #6; Rooms IDF #636; Electrical Room #664; corridor shaft #550.
12/19/2019 FRAMING Not ready for Inspection Contractor cancelled.
12/18/2019 FRAMING Partial Approval Level #5; Rooms: 500, 501; 502; 503; 504; 505; 507; 530; 532; 534; 536; 533.
12/17/2019 FRAMING Cancelled Contractor cancelled, reschedule for 18 December.
12/16/2019 FRAMING Partial Approval Level #5; Room 509.
12/12/2019 FRAMING Partial Approval Level#5; rooms 520; 521; 522. Ok to cover progress areas.
12/10/2019 FRAMING Partial Approval Level #5; North, Rooms: 511; 513; 515; 517; 518; 519; 521
12/09/2019 FRAMING Partial Approval Level #3; Rooms: 371; 372C; 372A; 372B; 370A; 370B; 370C. Level #4; East exterior wall at GL: H/1-4
12/06/2019 FRAMING Partial Approval Level #4; Rooms: 430; 431; 432; 433; 434; 436.
12/05/2019 FRAMING Partial Approval Level #4; East and South parapet walls. Ok to cover progress areas.
12/02/2019 FRAMING Partial Approval Level #4; Rooms: 414; 420; East; South; and West exterior walls; interior courtyard walls.
11/27/2019 FRAMING Partial Approval Level #3 Parapet wall; ensure proper screw pattern is in place.
11/26/2019 FRAMING Partial Approval Level #3; Rooms #309; 312; 349; 351. Level#4; Rooms: 463 and 464. Level #5 (partials) 563, 564. Ok to hang sheet rock in progress areas.
11/22/2019 FRAMING Partial Approval Condensing lines 4 each lines at 1 1/2” lines on levels #2 and #3; supply and return lines in parking garage; 2 lines at 6”: tested at 120 psi. Waste and vent lines at 2”-4” on Levels 3; 4; 5 (North portions).
11/20/2019 FRAMING Partial Approval Level #4; Rooms: 400; 401; 402; 403; 404 (partial); 405; 412; 413; 421. Ok to cover walls in progress areas.
04/29/2019 FRAMING Prior to Intermediates Desing Review must be completed and approved prior to approval of this inspection.