Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
Permit Number - T16CM02856
Inspection Description - FRAMING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2020 | FRAMING | Approved | ||
| 04/09/2020 | FRAMING | Partial Approval | RVI Stairwell #2; Levels #2-#14; hand rail backing in place. Ok to insulate and cover walls. | |
| 04/08/2020 | FRAMING | Partial Approval | RVI Stairwell #1; Levels: Garage through Level #15. Ok to insulate and cover the walls. | |
| 04/06/2020 | FRAMING | Partial Approval | RVI-Trash chutes at Levels 1-7 | |
| 04/02/2020 | FRAMING | Approved | #7; all room units and fitness area. | |
| 03/20/2020 | FRAMING | Partial Approval | Level #15, Hotel bar roof parapets at GL: 3.4/D-E.6; E.6-F.5/2.2; 2.2-4/F.5; 7.8/A-B, A/7.8-9.8; 9.8/A-C. Ok to cover walls. | |
| 03/19/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 03/18/2020 | FRAMING | Partial Approval | Level #12; Rooms #1200; 1201. | |
| 03/17/2020 | FRAMING | Partial Approval | Level #6; Rooms: 630; 631; 632; 633; 634; 636. Exterior wall framing at GL: 12/A-D.3; D.3/12-9; 9/D.3-H; H/9-7.1. | |
| 03/13/2020 | FRAMING | Partial Approval | Level #15 parapet walls; Northwest parapet walls at 6’7"; East side center portion of parapet wall at 10’2". Ok to cover progress areas. | |
| 03/12/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 03/11/2020 | FRAMING | Not ready for Inspection | Canceled by contractor. | |
| 03/10/2020 | FRAMING | Partial Approval | Level 15; Roof Terrace at GL: 3.4/D-E.9; E.9/3.4-3.2; 3.2/E.9-F.5; F.5/3.2-4; G/4-1.8; 1.8/G-E.5; E.5/1.8-3. 01036. Not ready. Contractor cancelled | |
| 03/09/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 03/06/2020 | FRAMING | Partial Approval | Level #5; Interior and exterior framing: 504; 530; 531; 532; 533; 534; 536. Level #12; Interior framing, Rooms: 1211; 1230; 1231; 1232; 1233; 1236. NOTE: At approximately 1000 hours, a tool gang box from CECO Concrete fell from level #14; Southwest area. The box impacted in the street between The Collective and the Marriott Hotel. No injuries were sustained and the proper authorities were notified. The box was removed and work in the area continued. Cause of the falling box is unknown to this Inspector at thIs time, |
|
| 03/05/2020 | FRAMING | Partial Approval | Level #15 High Roof, Elevator Lobby: East, North, West walls. North Elevator shaft framing from Basement level to Level #15. Ok to fire caulk shafts. |
|
| 03/04/2020 | FRAMING | Partial Approval | Level #12; unit framing at Rooms: 1203; 1205; 1207; 1209; 1210; 1212. | |
| 03/03/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/28/2020 | FRAMING | Partial Approval | Level #4; Rooms: 431; 434; 436. | |
| 02/27/2020 | FRAMING | Partial Approval | Level #4, Rooms: 430; 432; 433. | |
| 02/26/2020 | FRAMING | Not ready for Inspection | Contractor cancelled | |
| 02/25/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/24/2020 | FRAMING | Partial Approval | Level #11; Rooms: 1100; 1101; 1102; 1103; 1105; 1107; 1109; 1110; 1112; 1163; 1164. | |
| 02/21/2020 | FRAMING | Partial Approval | Stairwell frame in units 344, 348, 350, 354 ok | |
| 02/20/2020 | FRAMING | Partial Approval | Level #15; Elevator Lobby exterior walls and roof; Room #1581; North, South and West walls; West portion of roof. | |
| 02/19/2020 | FRAMING | Not ready for Inspection | Contractor cancelled | |
| 02/14/2020 | FRAMING | Not ready for Inspection | Canceled | |
| 02/13/2020 | FRAMING | Partial Approval | Level #10; Room #1010. | |
| 02/12/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/11/2020 | FRAMING | Partial Approval | Level #10; Rooms: 1000; 1001; 1002; 1003; 1005; 1007. | |
| 02/10/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/07/2020 | FRAMING | Not ready for Inspection | Contractor cancelled | |
| 02/06/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/05/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 02/04/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/31/2020 | FRAMING | Partial Approval | Level #9; Rooms: 900; 901; 902; 903; 904; 905; 907; 909; 910; 911; 912; 965. | |
| 01/30/2020 | FRAMING | Partial Approval | Level #1; 3 each columns at GL: H/8.8; H/7.9; H/7.1. Ok to cover progress areas. | |
| 01/27/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/26/2020 | FRAMING | Partial Approval | Units 511 and 513 electrical and mechanical OK. Unit 510 mechanical still needs attention.Electrical in 510 approved. | |
| 01/24/2020 | FRAMING | Partial Approval | Level #8; Rooms: 800; 801; 802; 803; 804; 807; 809; 810; 811; 812; 805. | |
| 01/23/2020 | FRAMING | Partial Approval | Level #5; Rooms 509; 512. In wall electric | |
| 01/22/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/17/2020 | FRAMING | Not ready for Inspection | ||
| 01/16/2020 | FRAMING | Not ready for Inspection | Per super | |
| 01/15/2020 | FRAMING | Partial Approval | Level #6; Rooms: 600; 601; 602; 603; 604; 605; 607; 610; 612. | |
| 01/14/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/13/2020 | FRAMING | Partial Approval | Level #6; Rooms, 613; 615; 617; 618. Level #7; Corridor #760; 763; 764. | |
| 01/10/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/09/2020 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 01/07/2020 | FRAMING | Partial Approval | Level #6; Rooms: 609; 630; 632; 634. | |
| 01/06/2020 | FRAMING | Not ready for Inspection | Rescheduled for 7 January. | |
| 12/31/2019 | FRAMING | Partial Approval | Level#6; Rooms: 611; 620; 621; 622. | |
| 12/24/2019 | FRAMING | Not ready for Inspection | Contractor cancelled. Crew sent home due to rain. | |
| 12/20/2019 | FRAMING | Partial Approval | Level#5; Rooms 510; 512; Level #6; Rooms IDF #636; Electrical Room #664; corridor shaft #550. | |
| 12/19/2019 | FRAMING | Not ready for Inspection | Contractor cancelled. | |
| 12/18/2019 | FRAMING | Partial Approval | Level #5; Rooms: 500, 501; 502; 503; 504; 505; 507; 530; 532; 534; 536; 533. | |
| 12/17/2019 | FRAMING | Cancelled | Contractor cancelled, reschedule for 18 December. | |
| 12/16/2019 | FRAMING | Partial Approval | Level #5; Room 509. | |
| 12/12/2019 | FRAMING | Partial Approval | Level#5; rooms 520; 521; 522. Ok to cover progress areas. | |
| 12/10/2019 | FRAMING | Partial Approval | Level #5; North, Rooms: 511; 513; 515; 517; 518; 519; 521 | |
| 12/09/2019 | FRAMING | Partial Approval | Level #3; Rooms: 371; 372C; 372A; 372B; 370A; 370B; 370C. Level #4; East exterior wall at GL: H/1-4 | |
| 12/06/2019 | FRAMING | Partial Approval | Level #4; Rooms: 430; 431; 432; 433; 434; 436. | |
| 12/05/2019 | FRAMING | Partial Approval | Level #4; East and South parapet walls. Ok to cover progress areas. | |
| 12/02/2019 | FRAMING | Partial Approval | Level #4; Rooms: 414; 420; East; South; and West exterior walls; interior courtyard walls. | |
| 11/27/2019 | FRAMING | Partial Approval | Level #3 Parapet wall; ensure proper screw pattern is in place. | |
| 11/26/2019 | FRAMING | Partial Approval | Level #3; Rooms #309; 312; 349; 351. Level#4; Rooms: 463 and 464. Level #5 (partials) 563, 564. Ok to hang sheet rock in progress areas. | |
| 11/22/2019 | FRAMING | Partial Approval | Condensing lines 4 each lines at 1 1/2” lines on levels #2 and #3; supply and return lines in parking garage; 2 lines at 6”: tested at 120 psi. Waste and vent lines at 2”-4” on Levels 3; 4; 5 (North portions). | |
| 11/20/2019 | FRAMING | Partial Approval | Level #4; Rooms: 400; 401; 402; 403; 404 (partial); 405; 412; 413; 421. Ok to cover walls in progress areas. | |
| 04/29/2019 | FRAMING | Prior to Intermediates | Desing Review must be completed and approved prior to approval of this inspection. |