Permit: T16CM02856

Parcel: 12404100A


Addresses:

930 E 2ND ST


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T16CM02856

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
05/20/2020 EXCAVATION/LAYOUT REBAR & ZON Approved
03/09/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #15; slab top finish; 4" wire mesh reinforcement. Ok to place 5" slab.
02/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Linen chute catch pads (#4 wire mesh - 4" slabs); Levels #2-#14: Ok to place concrete in progress areas.
02/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #15; Screen wall at GL: B.5/1.5-3.5; Apartment side exterior pool walls at 6’8") at GL: 6.9/D-G.5; G.5/9.1-6.9; 9.1/D.3-H; South walls at D.3/9.1-12; 12/D.3-A; A/12-9.5. Ok to place concrete in progress areas.
02/05/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #15; parapet walls - North and Northeast areas. Ok to place concrete in progress areas.
01/27/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Level - Roof North; will reschedule for 28 January.
01/22/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #13 South, Post Tension Cable System. Ok to place concrete in progress areas.
12/16/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #11 South CMU Columns at GL: A/7.8; A/9; A/10; A/12; B/7; B/7.8; B/9: B/10; B/12; C.1/11; C.1/12; C/7; D.3/11; D.3/12; D.7. Ok to place concrete in progress areas.
12/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #10 South; Concrete columns at GL: A/7.8; A/9; A/10; A/12; B/7; B/7.8; B/9; C.1/11; C.1/12; B/10; B/12; C/7; D.3/11; D.3/12; D/7. Pk to place concrete in progress areas.

Note: Level #10 South Post Tension Cable System was inspected completely by GTI Inspector Fernando on 4 December.
12/02/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/27/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled
11/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #3; Spa double mat rebar (#372). Ok to place concrete.
11/22/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/21/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled.
11/20/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North core - Elevator #2 and Stairwell #2 at Level #9 North. Columns at GL: F.5/2; G.5/1; G/3; G/4; H/1.8; H/3; H/4. Ok to place concrete in progress areas.
11/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #9 North, columns at GL: A/1.8; A.2/1; A/3; A/4; B.5/1; B.5/2; B/3; B/4; B/5; B/6; C.3/1; C.3/2; C/6; D.4/1; D.4/2; D/6; E.6/1; E.6/2; E/3.4; E/4; F/3.4; F/4; F.5/1. Ok to place concrete in progress areas.