Permit: T16CM02494

Parcel: 11202003D


Addresses:

3838 N CAMPBELL AV

Inspection Status: Partial Approval

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
09/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM FOOTING AT GL: D/10.5 - 14. OK TO POUR PROGRESS AREA.
08/30/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS AND CURBS, GL: F - G/14 -17; G - H/15 - 16.
08/30/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL: 8/C - G; 9/C, D, F, G, H; SHEAR WALL AND FOOLTINGS AT GL: G/8 - 9; 9/G - H. OK TO PLACE PROGRESS AREAS.
08/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL: D - G/3 -4; F/5 - 6; FORMED, OK TO PLACE PROGRESS AREAS. SHEAR WALLS: GL: C/5-6, G/5-6
08/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval MAT FOUNDATION AT GL: A/1 - 3.5, C/1 - 3.5; C - E.75/1 - 2; COLUMN FOOTINGS AT GL: E/8 (F5); D/9 (F5) PLUS PEDISTAL AT D/9.3; C/9 (F4) PLUS PEDISTAL C/9.3. GRADE BEAM AT D/18 - 20. OK TO POUR PROGRESS AREAS.
08/17/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS (FORMED) AT GL: 11/D (F4); E/(F5); F (F5); G (F5); LEVEL 1 STAIRWELL WALLS (STAIRWELL #4); OK TO POUR PROGRESS AREAS.
08/16/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS (F5), AT GL: 3/D, E, F, AND GL: 8/D, E. OK TO POUR PROGRESS AREAS
08/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 11/ D, E, F, G; 10/G; 10.3/D; 8/C; 4/E. COLUMNS (FORMED) AT GL: 7/ C, D, E, F, G; 6/D, E, ; 5/D, E; 12/ D, H. OK TO POUR PROGRESS AREAS.
08/09/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection RAINED OUT
08/08/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 2/G (F2), G/3 (F3), G/4 (F5), E/4 (F5), F/4 (F5). OK TO POUR PROGRESS AREAS.
08/05/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHEAR WALL FOOTING AT GL: C/5 - 6. OK TO POUR PROGRESS AREA.
08/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHEAR WALL FOOTING AT GL: G/5 - 6 (2 @F7 FOOTINGS INCLUDED); COLUMN FOOTINGS AT GL: C/7 (F4), D/7 (F5), E/7 (F5), F.7 (F5), F5 FOOTINGS AT GL: D/6, E/6, F/6. OK TO OUR PROGRESS AREAS
08/02/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection RAINED OUT, WILL RESCHEDULE
08/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHEAR WALL FOOTINGS AT GL: G/8 - 9; 9/G - H; G/5 - 6, NEED DOWELS, RECALL FOR COMPLETION INSPECTIONS
07/29/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS ON GL: 7/C, (F4), 7/D (F5), 7/E (F5), 7/F (F5), 7/G (F4). OK TO POUR PROGRESS AREAS.
07/28/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (26 JULY) REBAR AND INTERIOR FORMS. AT ELEVATOR SHAF; OK TO CLOSE UP FORMS (B STEVENS) (27 JULY): STEM WALL AT GL: 20/D - H; SHEAR WALL #19 AT GL: 19/D - F; COLUMN FOOTINGS AT GL: 12 (EAST)/ D - H. OK TO POUR PROGRESS AREAS.
07/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval MATT FOOTING 4'6" AT GL: 14 - 15/ G.6 - H. OK TO POUR PROGRESS
07/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS ON GL: 12/ E, F, G, H. (F5) FOOTINGS. OK TO POUR PROGRESS AREAS.
07/21/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 13/D, E, F, G, H; GL: 14/D, G. SHEAR FOOTING AT GL: 14/E - F. OK TO POUR PROGRESS AREAS.
07/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL: 15 (4' ONE COLUMN; 5' THREE COLUMNS); LINE 16 (4' ONE COLUMN, 5' THREE COLUMNS) OK TO POUR PROGRRESS AREAS.
07/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 14/D (F4), 14/G (F5), GL: 13/D (F4) 13/E (F5), 13/F (F5), 13/G (F5), 13/H (F4). GRADE BEAM SHEAR FOOTING AT GL: D/E - F. OK TO POUR PROGRESS AREAS.
07/18/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL; 20 (5), 19 (3), 18 (4), 17 (3). OK T SET FORMS AND POUR
07/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F4 COLUMN FOOTINGS AT GL: E/15, G/15, E/16, F/16, G/16, F/15. GRADE BEAM FOOTING AT GL: D/17 - 18. OK TO POUR PROGRESS AREAS.
07/14/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR PIT FOOTINGS/STAIRWELL FOOTINGS - GL; 8.25 - 10/ D.5 - E.5. OK TO POUR PROGRESS AREAS.
07/13/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL; H/17, (1 F3 FOOTING); 3 EACH F5 FOOTINGS AT GL: 17/E, F, G,. SHEAR WALL FOOTING AT GL; 19/ F - G. CENTER STAIRWELL AND ELEVATOR FOUNDATIONS AT GL; 8.25 - 10/ D.5 - E.5. OK TO POUR PROGRESS AREAS.
07/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS: 4 @ F5 ( 1 @ GL: 19/E; 3 @ 18/E, F, G. 2 @ F3 COLUMNS AT GL: 19/D, 18/H. OK TO POUR PROGRESS AREAS
07/11/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WALL FOOTINGS (WF3) GL: 20/ D - H. 5 EACH F1 COLUMNS AT GL: 20/ D - H; COLUMN FOOTING (F3) AT GL: 19/H. OK TO POUR PROGRESS AREAS.