Permit: T16CM02493

Parcel: 11202003D


Addresses:

3838 N CAMPBELL AV

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
12/26/2017 EXCAVATION/LAYOUT REBAR & ZON Approved
10/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PILASTER FOOTINGS AT GL; 7/ D.1; 7.5/ D.1; 9/D.2. OK TO POUR PROGRESS AREAS.
10/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR FOOTING, COLUMN FOOTINGS, PEDISTALS AT GL: CE - CE.9/7; DE.5 / 7 - 7.8. OK TO PLACE CONCRETE.
10/06/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
10/06/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
10/04/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PEDISTAL AND COLUMN FOOTINGS AT GL: DE/8; A/7.9 (D.6); CE.9/7.5. OK TO PLACE CONCRETE IN PROGRESS AREAS.
09/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS (F2); WALL FOOTING (SW4 - WF8) GL: CE/10 - 17. OK TO PLACE CONCRETE
09/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHEAR WALL FOOTING (SW3 - SF7) AT GL: 18/ BE.75 - CE.25. OK TO PLACE CONCRETE.
09/21/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTING @ GL: AE/8 - 9 (F4); SHEAR WALL FOOTING (SW3 - WF3) @ GL: 18/AE.75 - BE.25. OK TO PLACE PROGRESS AREAS.
09/21/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: E/15, 16, 18 (F4"S), #17 (F3). OK TO PLACE CONCRETE
09/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: BE/17 (F2), 11/BE (F2); WALL FOOLTING AT GL: BE/11 - 17 (WF4) AT GL: BE/11 - 17; OK TO PLACE CONCRETE.
09/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: AE/16 - 17 (F3 - F4). DE/ 13 - 16 (F4); SHEAR WALL FOOTING AT GL: CE/ 8 - 9. OK TO PLACE CONCRETE AT PROGRESS AREAS.
09/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: DE/ 13 - 16. OK TO PLACE CONCRETE AT PROGRESS AREAS.
09/12/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WILL RECALL FOR 14 SEPTEMBER 2016
09/09/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: AE/11, 12, 13, 14, 16; SHEAR WALL FOOTING AT GL: BW/8 - 9.
NOTE: COLUMN FOOTING AT GL: AE/15 WAS TOO WET TO POUR AT THE TIME OF THIS INSPECTION; WILL NEED TO DRY-OUT. OK TO POUR PROGRESS AREAS.
09/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WF5 FOOTING AT GL: DW/1; CW.9/1. OK TO POUR PROGRESS AREAS.
08/31/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5 EACH COLUMN FOOTINGS AT GL: DW/2 (F3), DW/ 3, 4, 5, 6 (F4); SHEAR WALL AT GL: CW/ 3 - 4
08/30/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 5/1; 6/A; 7/A; (F4); GL: 5/B; 6/B, C (F2); SHEAR WALL FOOTINGS AT GL: B/3 - 4. OK TO PLACE CONCRETE.
08/26/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED
08/25/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS CW/2 (F1), CW/5 (F2)..COLUMNS POURED.
08/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS AT GL: AW/1 - 1.25; 1/AW.8 - BW.5. OK TO POUR PROGRESS AREAS.
08/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS AT GL: 2/ AW(F3); 3/AW (F4); 4/AW (F4); 2BW (F1). OK TO POUR PROGRESS AREAS.