Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 06/07/2016 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Approved |
|
| 05/20/2016 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
hydro approved. upright closest to west door is >10' from wall. cooler and freezer walls need to have walls to ceiling or add heads. currenly no walls so need to add heads. |
| 04/27/2016 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
Ok to place hard lid and drywall |