Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/09/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Inspect completed patch. Structurally sound but very poor workmanship. Will keep an eye on it until mill and overlay is performed when the UofA is out of session. |
| 01/14/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Patch trench. |
| 01/11/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Backfill trench with CLSM 2. |
| 01/05/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Observe project. Inspect traffic control. |
| 01/04/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Observe beginning of project. Inspect traffic control and make changes to taper and buffer zone on WB side. |