Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T15CM03386

Parcel: 11506207B


Addresses:

1801 N STONE AV


Inspection Status: Approved

Inspection History: FIRE - FINAL

Permit Number - T15CM03386

Inspection Description - FIRE - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
01/06/2016 FIRE - FINAL Approved
12/24/2015 FIRE - FINAL Partial Approval TCO already approved. Only waiting on as builts for hood system.
12/23/2015 FIRE - FINAL Denied 1) Repair emergency light, upstairs hallway.
2) Need as built submitted for kitchen hood.
3) Mount occ. load sign
4) Install panic on all doors, including door next to bar, NW side.
_Will give partial and TCO approval once 1,3, &4 are completed.
12/23/2015 FIRE - FINAL Partial Approval Partial approval. Still need as built for hood system. Emergency light installed in upstairs hallway. Panic hardware installed on both sets of double doors NE corner. We still need panic hardware installed on single door, NW corner, next to bar. Per acting building official, Trevillyan, Clayton, they are approved to open for business with a fire watch established at the that does not have panic hardware.
12/18/2015 FIRE - FINAL Denied 1) Label riser room door. "riser room"
2) Label the same door "FACP"
3) Exposed electrical wires in riser room.
4) Electrical not finished throughout building.
5) Repair emergency lighting unit, upstairs hallway.
6) Resolve deficiencies on annual sprinkler report. Provide invoice or updated report.
7) Panic hardware required on all doors.
8) Need as builts for hood system. Approved plans do not show griddle.
12/16/2015 FIRE - FINAL Denied 1) Need sprinkler final.
2) Need panic hardware on all doors.
3) Exposed electrical throughout. Cover plates open, open junction boxes, etc...
4) We need to test all emergency lights and exit signs.
5) Need annual and 5yr check valve inspection reports with no deficiencies.
6) Patch drywall holes throughout building.