Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/22/2016 | PLUMBING - INTERMEDIATE | Approved | ||
| 07/18/2016 | PLUMBING - INTERMEDIATE | Partial Approval | LIVING UNITS FROM TOWNHOUSES TO 4TH LEVEL | |
| 07/14/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | ||
| 07/07/2016 | PLUMBING - INTERMEDIATE | Partial Approval | PRELIMINARY WALK THROUGH OF ROOMS ON LEVEL #5: ROOMS 515 - 522 | |
| 06/01/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 6TH FLOOR NORTH WING; WASTE AND VENT LINES TESTED. OK TO COVER WALLS | |
| 05/27/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | CONTRACTOR CANCELLED | |
| 05/26/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | ||
| 05/25/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | 6TH FLOOR WASTE AND VENT LINES NOT FULL FOR INSPECTION | |
| 05/16/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 6TH FLOOR ABOVE CEILING AND IN WALLS (SOUTH) | |
| 05/16/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ROOMS #705 & 704; OK TO INSULATE AND SHEETROCK | |
| 05/12/2016 | PLUMBING - INTERMEDIATE | Partial Approval | SIXTH FLOOR SOUTH DWV OK TO COVER. | |
| 05/04/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | ||
| 04/26/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 5TH FLOOR WALLS | |
| 04/25/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/22/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/19/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/18/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/12/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 4TH FLOOR WALLS NORTH AND SOUTH; OK TO INSULATE | |
| 04/12/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 04/11/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 04/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 4TH FLOOR SOUTH WALLS ONLY | |
| 04/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 04/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | 4TH FLOOR EAST; WALLS ONLY | |
| 04/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 04/07/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 04/06/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/06/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | ||
| 04/05/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/01/2016 | PLUMBING - INTERMEDIATE | Partial Approval | ||
| 03/31/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/30/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/29/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/23/2016 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection :23No Description.| 99946 * |
|
| 03/21/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/17/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/16/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/10/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/08/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/08/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/04/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/01/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 02/26/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 02/26/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 02/24/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 02/12/2016 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 02/10/2016 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* |