Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/05/2016 |
BUILDING ABOVE CEILING |
|
Approved |
|
| 06/24/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
LOBBY AREAS - R00M #104 |
| 06/20/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
6TH FLOOR NORTH AND EAST - OK TO COVER |
| 06/15/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
6TH FLOOR SOUTH, EAST TO ELEVATOR LOBBY - OK TO COVER |
| 06/07/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
1ST FLOOR MEZZANINE HALLWAY AT ELEVATOR AND FIRE PUMP ROOM. OK TO COVER. |
| 06/03/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
4TH FLOOR HALLWAYS - OK TO SHEET ROCK |
| 05/26/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
2ND FLOOR EAST ROOMS #223 AND 224 (SSK-52), OL TO COVER PROGRESS AREAS. |
| 05/25/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
4TH FLOOR SOUTH HALLWAY. OK TO COVER PROGRESS AREAS. |
| 04/14/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |