Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/09/2016 | FIRE SPKLR - OH PIPING & HYDRO | Approved | ||
| 01/26/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Navarrete on site. They made corrections that nsprenger noted. Still needs the following. 1) Wire bell next to riser and it needs to be tested. 2) Monitoring not needed. 13D system with no control valve. Connected straight to domestic. |
|
| 12/21/2015 | FIRE SPKLR - OH PIPING & HYDRO | Denied | There is no check valve, flow switch, electric bell or 1/4 inch gauge and 1/2 inch drain valve. System is a D, but there are 5 occupants in this assisted living and the system's flow switch will need to be monitored, with a pull and smoke near an annunciator/control panel interior. Will need seperate alarm permit for installation of monitoring and smoke,flow, pull, control panel installation. | |
| 12/17/2015 | FIRE SPKLR - OH PIPING & HYDRO | Denied | can not see hangers on pipe ( insulation on pipe). Mark where hangers are. | |
| 12/14/2015 | FIRE SPKLR - OH PIPING & HYDRO | Denied | Not ready still installing pipe and hangers, need to check sprinkler coverage inside each room, was advised to insulate all piping. |