Inspection Status: Partial Approval
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
Permit Number - T15BU00659
Inspection Description - FIRE SPKLR - OH PIPING & HYDRO
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial approval for Fire Pump acceptance test. | |
05/05/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for 6th floor. | |
04/29/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Ok to hard lid 5th floor. | |
04/26/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. OH/Piping Hydro Ok for 5th floor. 2. Need to move duct work and sprinkler heads away from one another. |
|
04/25/2016 | FIRE SPKLR - OH PIPING & HYDRO | Cancelled | cancelled by contractor due to pressure loss in system from a leak. will call it in again for tomorrow. | |
04/22/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Ok to hard lid 4th floor. | |
04/21/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for 4th floor. 2. Need insulators to remove insulation on uprights before hard lids are installed. |
|
04/08/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for 3rd floor. | |
03/21/2016 | FIRE SPKLR - OH PIPING & HYDRO | Denied | upright coverage above ceilings in rooms on third floor is being compromised by placement of Hvac duct work coming in after sprinkler heads have been installed. pressure on third floor was not at 200 psi when read. | |
03/15/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for Mezzanine. | |
02/29/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for Garage, Town Houses, and 2nd Floor. |