Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T14CM06286
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2016 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
09/29/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/28/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 STAIR ON GRADE | |
08/31/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/28/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LINE 6/7 | |
08/21/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/20/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RAMP AREA GL: E.5-E.9/3.5-6 | |
08/18/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
08/10/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTING LINE F/7.8, F.4/7-7.8, G/7.5-7.8 | |
08/06/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/05/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ONE COLUMN L-1.3/D (?) - 1ST TO 2ND LEVEL | |
08/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/03/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS GL 1.3/A, B, B.9, D, E, F, 2/A.B.C.D.E.F, 3/F - 1ST FLOOR TO 2ND, SLAB ON GRANDE, H/3.5-4.2, F-3/3.2 | |
07/31/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
07/28/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
07/27/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GENERATOR PAD. FOOTERS AT GL: A/7-8, 2.7/A.B5, A/7.7-8, 8/A-B.5 | |
07/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL A-F.8/1-3.5 | |
07/22/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL A/3-7.7 H/1.3, 1.5, 2, 2.2 |
|
07/21/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
07/17/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | footing stairwell #1 WALLS | |
07/15/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PER DETAIL 107 | |
07/14/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RFI W8 OK ON SOUTH SHEAR WALL STEM WALL EAST PLANTERS |
|
07/10/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ||
07/08/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STEM WALL GL F8/1.9 TO G/1.9-2 AND 2/F.9 TO G - ALL OK TO POUR. | |
07/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO GROUT TO 4'8" H/5,6;F/5,6;6/F-H AND 2.5/G-G6 TO 5'4" ELECTRICAL UNDER ELECTRICAL ROOM OK TO COVER (GL F6/7-8) OK TO POUR COL A/7.7 TO SECOND FLOOR. WALL F5.5 / 1-1. OK TO POUR TO 54" |
|
07/06/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN G/1.3 OK TO POUR TO SECOND FLOOR | |
07/02/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL: 1.3/F.5 OK TO POUR PROGRESS | |
06/30/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS GL:1-3/H, 2/6-8,2-8/6,6.6 3.8/ 6-8 6/F-6, G.6 FOOTINGS GL:F/5.2-6; 6/F-H, 2.8-6;2-8/F-H F/2.8-4; G/ 1.7-2.5; CAISSON CONNECTIONS GL;1-2/F-5, 2/G-F SHEAR WALL FOOTING ; F/4-5. | |
06/29/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS LINE 1.3/F,E,A | |
06/25/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4 @ CAISSON CAPS GL 1/F.8, G.6; 7/ F.8, G.8 OK TO POUR PROGRESS AREA | |
06/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMS 1, 3/C2 3/DE 4DF 3.8 /G-G.6 CAISSONS CAPS H/1.3, G8/2 | |
06/23/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSON CAPS: GL: F/3.4,4.5, 5.6 G/2.8, E/4,5 COLUMNS F-4/1-9, F/2 OK TO POUR PROGRESS AREAS |
|
06/22/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
06/17/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISONS LINE 4/5/6-E,G/7F CAISON CAPS LINE 2 A,D,1.3A, 3C, 4C, 5C, 6B,C |
|
06/16/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL, CASONS LINE F/ 4.5 5.6, 7/ OE. CAISORS CAPS 5/0, 6/A, 7/A, 8C | |
06/15/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
06/12/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL2/F.5, 25/F.3, F.0, 5/D, 6/C,D. 7/B,C,A. 7.7/C,A,B. 1/F.8 4CF-3, 4.CF1. CAGES IN PLACE |
|
06/11/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | (11) CAGES 9 F2, 1 F3, 1 F4, CAISSON HOLE 11, GL.C.3/A, C.5, 2/A, B, C, D, 4/A, B, C, D, 5/A, B, C | |
06/10/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
06/10/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSON COLUMNS - IN PLACE 6 @ CF2, 6 @ CFI GL: 1-3/DEF, 3/A, B, C, D, E, F: 16 @CFI CAGES; 1 CF2 CAGE - OK TO POUR PROGRESS AREAS | |
06/09/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 16 CAGES PER 104 DETAIL. 9 HOLE VERIFIED, 4 IN PLACE | |
06/08/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 13 CAISONS (RE-BAR RACKS) PER DETAIL 104 ABOVE GROUND OK TO PLACE. |