Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
Case Number - T13DV09038
Inspection Description - INSP - FOLLOW UP CODE ENFORCE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/16/2014 | INSP - FOLLOW UP CODE ENFORCE | Approved | Spoke with the superintendant and the Lath foreman. They wil buy more tarps as necessary to control and maintain the loose particles. 5 day follow up. | |
01/14/2014 | INSP - FOLLOW UP CODE ENFORCE | Approved | W. Navarro and myself visited the superintendant and talked to him about containment of the foam particles in the air. He assumed that they still had the tarp up covering thae areas of work, which they did not. He is going to address the situation with his aproprate sub contractor. 2 day follow up. | |
01/13/2014 | INSP - FOLLOW UP CODE ENFORCE | Approved | Follow up from a call from the office about styrofoam in the air. Went to site in the late afternoon and did observe flying foam. Will talk to superintendant in the morning. | |
01/10/2014 | INSP - FOLLOW UP CODE ENFORCE | Approved | Visited site, Superintendant is maintaining the site. I will hold open untill all stucco is installed. 20 day follow up. | |
12/19/2013 | INSP - FOLLOW UP CODE ENFORCE | Approved | Visited site and confered with superintendant. He is maintaining the site. I will hold open untill all stucco is installed. 20 day follow up. |