Inspection History Details
Inspection Status: Approved
Inspection History: ROOF NAILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2013 | ROOF NAILING | Approved | IVRS - Inspection :* | |
| 07/23/2013 | ROOF NAILING | Not ready for Inspection | northside 2nd floor toilet flanges ok to cover | |
| 07/19/2013 | ROOF NAILING | Partial Approval | sw third of cafe roof ok to dry in | |
| 07/19/2013 | ROOF NAILING | Partial Approval | truss bracing all ok per approved plan | |
| 07/15/2013 | ROOF NAILING | Not ready for Inspection | SOUTH WALL & W WALL NORTH TO CAFETERIA - OSB OK TO COVER ELEC OK 2ND FLOOR - S WALL TO ELEVATOR - ALL OK PLUMB NORTH TO CAFE - OK |
|
| 07/13/2013 | ROOF NAILING | Partial Approval | 2ND FLOOR & INTERIOR PARAPETS FOR SAME ARE OK ON WEST-SOUTH HALF UP TO LINE SETS. NOTE: CONTINUING WITH TRUSSES, SHEATHING, AND DRY IN IS DONE AT YOUR OWN RISK DUE TO TRUSS APPROVAL DILEMMA |
|
| 07/10/2013 | ROOF NAILING | Partial Approval | gym and 1st floor roof on northeast quarter of building ok | |
| 07/09/2013 | ROOF NAILING | Partial Approval | nw first floor roof (middle of building) ok | |
| 07/08/2013 | ROOF NAILING | Not ready for Inspection |