Inspection Status: Partial Approval
Inspection History: MECHANICAL - HOODS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* 1) SMOKE CONTAINMENT TESTED OK, STILL WAITING INTERLOCK INSTALL ON HOOD, HOOD BALANCE REPORT AND FIRE APPROVAL ON FIRE SUPRESSION SYSTEM, NEED MINIMUM OF FIRE APPROVAL IN ORDER TO LOOK AT TEMP C OF O |
|
| 05/15/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* | |
| 05/07/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* 1) CHECKED EXTENSIONS ON COOLERS, RAISE 2 SEWER VENTS 2' ABOVE COOLER EXTENSIONS |
|
| 05/04/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* 1) 2ND LAYER OF FIRE WRAP OK |
|
| 05/03/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* 1) 1ST LAYER FIRE WRAP OK, OK 2ND LAYER TO INSTALL |
|
| 05/02/2012 | MECHANICAL - HOODS | Partial Approval | IVRS - Inspection :* |