Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/26/2013 | FIRE SPKLR - FINAL | Approved | ||
| 07/23/2013 | FIRE SPKLR - FINAL | Partial Approval | tested all flow switches and tampers. | |
| 07/16/2013 | FIRE SPKLR - FINAL | Partial Approval | Partial approval given for moving in furniture when Kazal turns on sprinkler system with fire pump on line, Tested emergency switch over with fire pump running, emergency generator switched over in 19 seconds fire pump started back up no problems. Still need to test FACP to fire pump and generator. |
|
| 07/08/2013 | FIRE SPKLR - FINAL | Partial Approval | completed a flow test with pump rep. 2. still need to test with alarm installed alarm was not installed. 3. need to perform a generator test this was not hooked up. |