Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
Permit Number - T12BU01082
Inspection Description - FIRE SPKLR - OH PIPING & HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/19/2013 | FIRE SPKLR - OH PIPING & HYDRO | Approved | ||
05/16/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 14th floor 200lb test approved. | |
04/25/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 200 psi and placment for the following: basement south and north roof level south and north standpipes 1. Need to correct sprinkler coverage next to white waste pipe in the basement in the parkin=g area and the maintance room. 2. Add sprinkler coverage under 54" duct in the maintance area. |
|
04/16/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 13th floor two hundred pound test approved. | |
04/02/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 12th floor ohpt complete | |
03/27/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. 11th floor 200lb test approved. copper pipes blocking coverage in hallways. | |
03/19/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | OH Hydro approved 10th floor.****NOTE in common hallways need to check sprinkler coverage from duct work and piping as per statement date 2.11.2013. | |
03/15/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 9th floor 200 lb test ok | |
03/12/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 8th floor overhead psi 200 lb test approved. | |
03/05/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 6th and 7th floor complete | |
02/15/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 5th floor opht complete. | |
02/11/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 4th Floor - Unit K #403 Add head in the dinning area Common hallways need to check coverage some heads blocked by piping and is there going to be a drop ceiling? Need to keep a close eye in the washer dryer room head needs 18" clearance or follow table 8.10.6.2.2 NFPA 13 2010. |
|
02/01/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | ||
01/31/2013 | FIRE SPKLR - OH PIPING & HYDRO | Cancelled | IVRS - RI canceled | |
01/24/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 3rd floor complete | |
01/23/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 2nd floor opt complete. |