Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T12BU00169
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/12/2013 | GRADING - INTERMEDIATE | Approved | ||
01/09/2013 | GRADING - INTERMEDIATE | Continued | 1) PROVIDE VERIFICATION THAT THE STORM DRAINAGE PIPE WAS INSTALLED PER THE APPROVED GRADING AND DRAINAGE PLAN, ( SURVEY NOTES, ELEVATIONS, PICTURES...). 2) PROVIDE STORM WATER SELF INSPECTIONS. 3) PRIOR TO FINAL APPROVAL, PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD AND A CERT. AS-BUILT DRAWING 4) PROVIDE STD DETAILS USED FOR INSTALL OF PIPE. 5) CALL FOR INSPECTION FOR ANY CONCERNS AND/OR CHANGES |
|
12/14/2012 | GRADING - INTERMEDIATE | Continued | RAINING, NO ACTIVITY SEDIMENT CONTROLS IN PLACE | |
12/12/2012 | GRADING - INTERMEDIATE | Continued | WILL REQUIRE A CERT STATEMENT FROM THE ENG OF RECORD STATING THAT THE SITE WORK, GRADING AND DRAINAGE WAS COMPLETED PER THE APPROVED PLANS. WILL REQUIRE AN AS-BUILT DRAWING SHOWING WHAT WAS CONSTRUCTED. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
11/28/2012 | GRADING - INTERMEDIATE | Continued | NEW SUPERINTENDENT ( DAN HICKS 928-856-1946) 1) NEED PICTURES OF INSTALL OF STORM PIPE AND STORM PIPE CONNECTION TO EXISTING PUBLIC SRP 2) TOOK PICTURES OF TWO CATCH BASINS ALONG THE EAST SIDE OF THE BLDG 3) NEED APPROVAL OF TIE-INTO EXISTING STORM PIPE 4) NEED CERT STATEMENT FROM ENG OF RECORD 5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
11/27/2012 | GRADING - INTERMEDIATE | Continued | NO CHANGES AND/OR CONCERNS | |
11/16/2012 | GRADING - INTERMEDIATE | Continued | 1) CONTRACTOR INSTALLED STORM DRAIN PIPING ALONG THE NORTH SIDE OF BLDG. PIPE TIES-IN TO AN EXISTING 48" STORM PIPE. DAVE ROBERTS VERIFIED MATERIAL AND SIZE. 2) CONTRACTOR TOOK PICTURES OF INSTALLATION AND WILL SEND THEM TO ME. 3) CALL FOR INSPECTION PRIOR TO INSTALL OF REMAINING STORM PIPE AND AREA DRAIN. 4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. |
|
11/15/2012 | GRADING - INTERMEDIATE | Continued | 1) CONTRACTOR INSTALLING 100 LF OF PVC STORM DRAIN LINE ALONG THE WEST AND NORTH SIDES OF THE BLDG. 2) NO SIGNIFICANT STORM WATER CONCERS AT THIS TIME |
|
11/13/2012 | GRADING - INTERMEDIATE | Continued | STORM DRAIN INSTALLATION HAS BEEN COMPLETED ON THE NORTHSIDE OF THE BUILDING, BUT THE TIE-IN TOO THE EXISTING SYSTEM WAS NOT WITNESSED BY MYSELF. I ALSO DISCUSSED WITH THE CONTRACTOR WHAT IS THEIR EXPECTATIONS OF THE SITE DURING THE HOLIDAY, THEY WILL ENSURE THAT ALL ITEMS WILL BE ADDRESSED PRIOR TO THEIR LEAVING THE SITE ON 11/21/2012. | |
11/02/2012 | GRADING - INTERMEDIATE | Continued | 1) SITE SPECIFIC SEDIMENT CONTROLS HAVE BEEN INSTALLED AND APPROVED. 2) DAILY STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. 3) ENSURE ALL OFF SITE TRACKED SOIL IS SWEPT ON A ROUTINE BASIS. 4) A CONCRETE/MATERIALS WASH OUT IS ON SITE AND IS BEING USED. 5) CALL FOR INSPECTION FOR ANY CHANGES AND/OR CONCERNS OR ANY UNDERGROUND STORM WATER DRAINAGE INSTALLATION. POC: BRETT WILLIAMS/STRAIGHT LINE CONSTR. 928-856-1946 |