Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Permit Number - T11CM02899

Inspection Description - PLUMBING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
08/22/2012 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
08/06/2012 PLUMBING - INTERMEDIATE Partial Approval OK SUBWAY ROUGH
OK 3 WEST AND SOUTH OVERFLOW DRAINS
08/03/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
07/31/2012 PLUMBING - INTERMEDIATE Partial Approval DVW AT BAKERY OK, L AND H AT DELI AND BAKERY TEST OK, STILL NEED TO INSULATE PRIOR TO SHEET ROCK
07/25/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
DELI AND ELEC/MECH, AREA DWV OK TO POUR
07/17/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
07/16/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
06/27/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
OVER-FLOW DRAINS AND CENTER EAST TEST OK
COLD WATER PRESS TEST OK THROUGH OUT
COPPER AT AUTO CENTER OK
06/26/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
OK HW/CW AND DWV AT NORTH OF BUILDING EXCEPT TI
06/25/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
VENT LEAK RESTROOM AT COLUMN C6
OKAY PHARMACY AND CART STORAGE WEST DWV WALLS
OKAY PRESSURE TEST AQUARIUM WATER LINE
06/15/2012 PLUMBING - INTERMEDIATE Partial Approval 1. Auto Center Interceptor set and tested. All inlet, outlet, vent and connective piping OK. 2. South gang bathrooms, and breakroom wall: PVC DWV through roof OK. Copper and insulation OK. OK to over walls this area only. 3. Kitchen interceptor set, tested. All inlet, outlet, vent, and connection to sanitary sewer OK to cover.
06/08/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
05/14/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) USE CORRECT GAUGES FOR TESTING GAS PIPE
MEDIUM PRESURE/WELD PIPING TEST OK
2) 4 SETS OF PVC ROOF DRAINS AND OVERFLOWS ALONG THE FRONT OF BLDG OK FOR INSULATION
03/14/2012 PLUMBING - INTERMEDIATE Not ready for Inspection 1. Use 5/8" rod for PVC longer than 8". 2. Overhead copper water piping OK to insulate. 3. Siphonic roof drains OK to insulate. Water test Ok two East systems.