Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T11BU01211

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
05/01/2013 GRADING - INTERMEDIATE Approved
12/11/2012 GRADING - INTERMEDIATE Continued STILL WORKING ON D.G IN LANDSCAPING AREA.
10/25/2012 GRADING - INTERMEDIATE Approved
10/10/2012 GRADING - INTERMEDIATE Continued WORKING IN PARKING AREA ON NORTH SIDE OF BUILDING.
09/20/2012 GRADING - INTERMEDIATE Continued STARTED LANDSCAPE INSPECTION PER HIGH LIGHTED ON SMALL SET OF APPRVED PLANS.
09/18/2012 GRADING - INTERMEDIATE Continued STRIPING AND LANDSCAPING WORK ON NORTH SIDE OF BUILDING.
09/17/2012 GRADING - INTERMEDIATE Continued NORTH PARKING AREA INSALLING TREES. STRIPING NORTHWEST SIDE OF PARKING AREA.
09/13/2012 GRADING - INTERMEDIATE Continued NO CHANGE TO OUT SIDE BUILIDING FROM LAST INSPECTION.
09/11/2012 GRADING - INTERMEDIATE Continued NO CHANGE TO OUT SIDE BUILDING FROM LAST INSPECTION.
09/06/2012 GRADING - INTERMEDIATE Continued NO CHANGE FROM LAST INSPECTION.
08/31/2012 GRADING - INTERMEDIATE Continued GOT WITH CONTACTOR STRIPING STARTS IN OCTOBER.
08/29/2012 GRADING - INTERMEDIATE Continued NO GRADING ACTIVITY AT THIS TIME.
08/23/2012 GRADING - INTERMEDIATE Continued NO OUT SIDE ACTIVITY.
07/27/2012 GRADING - INTERMEDIATE Continued RON AND I WALKED THROUGH THE SITE AND LOOKED AT THE PAVEMENT SUBGRADES THAT HAVE BEEN PREPARE ON THE NORTH, WEST, AND SIDES OF THIS PROJECT. THE CONTRACTOR IS PLANNING ON PAVING THESE AREAS NEXT WEE, WEATHER PERMITTING.
07/26/2012 GRADING - INTERMEDIATE Continued CREWS WORKING ON PROCESSING THE GRADES ON THE NORTH SIDE FOR THE PLACEMENT OF ASPHALT PAVEMENT NEXT WEEK. HAVE ASKED THEM TO CALL IN THE INSPECTION FOR THE RAINWATER INTERMEDIATE SO THAT WE CAN CHECK THE GERADES TO MAKE SURE THAT THEY ARE MEETING THEIR REQUIREMENTS FOR THE SITE. CREWS ALSO WORKING ON POURING CONCRETE FOOTERS FOR BOLLARDS ALONG THE NORTHSIDE ENTRANCES.
05/30/2012 GRADING - INTERMEDIATE Continued STILL WORKING ON GRADING AND CURBING IN PARKING AREA.
05/16/2012 GRADING - INTERMEDIATE Continued GRADING FOR PAVING PARKING AREA.
05/08/2012 GRADING - INTERMEDIATE Continued STORM DRAIN PIPING INSTALL PER HIGH LIGHT ON PAGE C4.3.
05/07/2012 GRADING - INTERMEDIATE Continued WORKING ON STROM DRAIN AT GATE.
04/26/2012 GRADING - INTERMEDIATE Continued WORKING ON GRADING AND CURBING ON NORTH PARKING AREA.
04/18/2012 GRADING - INTERMEDIATE Continued LOOKED OVER THE SITE AND CHECKED THE INSTALLATION OF SEWER PIPE AND MANHOLES BEING CONSTRUCTED AROUND THE NORTHWEST AND SOUTHWEST CORNERS OF THE BUILDING. ALL INSPECTED AREAS ARE HIGHLIGHTED ON THE PLANS IN THE CONTRACTORS OFFICE.
04/12/2012 GRADING - INTERMEDIATE Continued BACK FILLING AROUND CATCH BASIN.
04/11/2012 GRADING - INTERMEDIATE Continued WORKING ON BASIN ON WEST SIDE OF BUILDING. NO PIPING BEING INSTALL TODAY.
04/10/2012 GRADING - INTERMEDIATE Continued FROMING AND INSTALLING CRUBING ON NORTH EAST PARKING LOT.
04/09/2012 GRADING - INTERMEDIATE Cancelled IVRS - AP canceled
04/06/2012 GRADING - INTERMEDIATE Cancelled IVRS - AP canceled
04/05/2012 GRADING - INTERMEDIATE Continued NO PIPING INSTALL CHANGE.
03/08/2012 GRADING - INTERMEDIATE Continued PER HIGH LIGHT ON C4.1.
02/22/2012 GRADING - INTERMEDIATE Continued NO CONCERNS AT THIS TIME.
02/14/2012 GRADING - INTERMEDIATE Continued NO CONCERNS AT THIS TIME.