Inspection Status: Approved
Inspection History: GRADING - CHECK FOR ACTIVITY
| Date |
Description |
Inspector |
Results |
Comments |
| 02/22/2013 |
GRADING - CHECK FOR ACTIVITY |
|
Approved |
|
| 11/20/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
GC NOT ON SITE WORK BEING DONE IN PARKING AREA AND ON SOUTH SIDE OF BUILDING |
| 08/22/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON THE LAST OF PAVING. |
| 08/21/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
PAVING ON WEST SIDE OF BUILDING. |
| 08/20/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
PAVING ON SOUTH SIDE OF BUILDING. |
| 08/17/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
PAVING ON NORTH AND EAST SIDE OF BUILDING. |
| 08/14/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
GETTING READY TO PAVE AREA JUST NORTH OF BUILDING. |
| 08/10/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
PAVING WORK BEING DONE ON SOUTH EAST SIDE OF JOB SITE. |
| 08/07/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
PAVING WORK HAS STARTED ON NORTH SIDE OF BUILDING. |
| 08/02/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
GOT WITH CONTRACTIR ABOUT MANHOLE COVERS. |
| 07/31/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
NO CONCERNS AT THIS TIME. |
| 07/30/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WALKED SITE WITH DAVE TO CHECK CRUBING AND GRADING . |
| 07/23/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON GRADING ON WEST SIDE OF BUILDING. |
| 07/18/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
GRADING WORK ON WEST AND EAST SIDE OF BUILDING . |
| 07/11/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON CURBING ON EAST SIDE OF BUILDING AND CHECKED CURB CUTS ON NORTH SIDE. |
| 07/02/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON CRUBING ON SOUTH EAST SIDE OF BUILDING. |
| 06/27/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON CURBING ON WEST SIDE OF BUILDING AND GRADING ON SOUTH AND EAST SIDE. |
| 06/18/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
NORTH EAST PARKING AREA PAVED. ON GRADING ACTIVITY TODAY. |
| 05/24/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
STILL WORKING ON GRADING FOR PAVING ON NORTH SIDE OF BUILDING. |
| 05/02/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON PARKING AREA. |
| 04/30/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
|
| 04/30/2012 |
GRADING - CHECK FOR ACTIVITY |
|
Continued |
WORKING ON GRADING AND CRUBING ON NORTH SIDE OF BUILDING. |