| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2012 | PLUMBING - FINAL | Approved | IVRS - Inspection :* 1) WITH THE EXCEPTION OF RED LINE CHANGES, ARCHITECT SUPPLEMENTAL INSTRUCTIONS, AND ON GOING CHANGES ORDERS, THE PLUMBING IS COMPLETE 2) SOME CHANGE ORDERS INCLUDE, BUT ARE NOT LIMITED TO: ROOF DRAINS-SCUPPER CHANGED AT GARAGE, ROOF DRAIN-SCUPPER CHANGED AT V.S.F., ROOF DRAIN-CHANGE AT ENTRY, DRAIN PIPING FROM FLAMMABLE WASTE/SAND SOIL SEPERATOR TO SANITARY SEWER AND ALL OUTSTANDING ASI'S 3) BACKFLOW CERTS ON SITE 4) RECEIVED CLEAN BACTERIA REPORT 5) ALL PIPING WAS INSTALLED PER UNAPPROVED CAD DRAWINGS |
|
| 01/25/2012 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* 1) 2ND FLOOR COMPLETE: SUBJECT TO M.O.S. AND CBR 2) 3RD FLOOR PLUMBING COMPLETE SUBJECT TO M.O.S. AND CBR |
|
| 01/20/2012 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) AS FINAL PROGRESS BEGINS-PLEASE HAVE: METHOD OF STERILIZATION AND CLEAN BACTERIA REPORT 2) A COMPLETE SET OF REVISED APPROVED PLANS, TO COMPARE WITH RED LINE "AS BUILTS" 3) 1ST FLOOR PLUMING IS COMPLETE-SUBJECT TO M.O.S. & CBR |