| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2012 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 01/18/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) UPPER AND LOWER HOSE BIBS GARAGE 2) SUPPORTS INSTALLED 3) ROOF DRAINS REQUIRE A REVISED APPROVED PLAN AND TEST |
|
| 12/23/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* NOBODY IN SUNDT TRAILER. UNABLE TO GAIN ACCESS. REINSPECTED: 4" TAPPED 8" MAIN PER DELTA 3 REVISION - NEED TO SEE REVISED APPROVED PLAN 4" UP TO BLDG ONLY |
|
| 11/21/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 1ST, 2ND & 3RD FLOOR OFFICE HEATING WATER 100 POUND TEST OK, EXCEPT ROOM 310-E AND 305-C OVERHEAD 2) MECHANICAL OK TO COVER 3) OK FOR GAS |
|
| 11/09/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1) A101B IN WALL WATER-OK TO INSULATE 2) GAS TEST OK |
|
| 11/08/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) A-101-B REWORK PLUMBING IN WALL OK TO COVER |
|
| 11/07/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) A115 E & D RESTROOMS OK TO INSULATE-THEN OK TO COVER 2) NEED TO SEE SHOWERS |
|
| 11/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) CONNECTION MADE OK TO RPPBP 2) ENTIRE SYSTEM UNDER TEST |
|
| 10/27/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 1ST FLOOR RESTROOMS WATER PIPING OK 2) OK FOR INSULATION |
|
| 10/26/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) N/H IN FIRST FLOOR RESTROOM OK 2) A-105 AND A-106 |
|
| 10/19/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) MAKE UP WATER TO COOLING TOWER COMPLETE TEST OK 2) ENTIRE ANNEX AND OFFICE OVERHEAD ON TEST AFTER ISOLATION VALVES INSTALLED |
|
| 10/13/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 2" TYPE "K" COPPER FROM MAIN BLDG TO VISITOR CENTER OK TO COVER |
|
| 10/08/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4" N/H VENT FOR SAND/SOIL SEPERATOR OK 2) TEST FOR SHOWER PANS ON FIRST FLOOR-BILL V. WILL VERIFY TEST ON REMAINING PANS |
|
| 10/06/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 10/05/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. SHOWER DRAINS TO BE TESTED 2. NO WORK MAY BE CONCEALED UNTIL IT HAS BEEN INSPECTED AND APPROVED ALL RE-WORK TO BE RETESTED |
|
| 10/04/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* SHOWER USER TO SEAL AT CORRECT CRACKING FOR POUR BACKET AT FHA SPLIT OF DRAIN |
|
| 10/03/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 09/30/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection : FLOORS IN SHOWER DO NOT SLOPE "REDGAURD" IS NOT SEALED AT DRAIN REFER TO HAND OUT CONCERNING SHOWERS REQ'D FHA DRAIN SUB FLOOR INSTALLED AND TESTED |
|
| 09/26/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) IN THE FUTURE, DO NOT USE TEST BLOCKS FOR DWV TEST, AS WHEN THEY ARE REMOVED AND A SPACER REPLACED, THERE ARE 2 UN-TESTED FITTINGS PER RISER 2) N/H TEST OK 3) WATER TEST OK 4) RAIN WATER LEADERS OK 5) NEED TO SEE CLOSET FLANGE |
|
| 09/22/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1) 3RD FLOOR OVER HEAD COMPLETE 2) MASONRY WALLS UP AT ANNEX |
|
| 09/09/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1) ROOF DRAINS AT ANNEX OK 2) WATER TEST OK 3) OVER FLOW IS PROVIDED BY SCUPPERS |
|
| 09/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* N/H DWV 2ND FLOOR OKAY WATER TEST COPPER INSTALLED OK INSULLATION OK |
|
| 08/30/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) TOILET ROOM 123-G MENS LOCKER ROOM 2) RE-ROUGH PLUMBING WALL TO ACCOMADATE ADA FIXTURES |
|
| 08/23/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 2nd FLOOR WATER DISTRIBUTION OK OK TO FINISH INSULATION |
|
| 08/17/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER PIPING OVERHEAD ON FIRST FLOOR AND DROPS IN THE WALLS OK |
|
| 08/15/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) NORTHEAST RESTROOM ROOM #114-A & 115 D-A OK TO COVER WALLS |
|
| 08/11/2011 | PLUMBING - INTERMEDIATE | Partial Approval | 1, water piping overhead on first floor and drops in the walls ok. | |
| 08/10/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) A-H AND 2-8 COLUMNS 2) BACKING INSTALLED BEFORE INSULATION 3) BACKING KNOCKING PLUMBING AROUND |
|
| 08/09/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) JOB NOW HAS COMPLETE AS BUILT PLAN. HAVE THESE APPROVED BY CITY OF TUCSON |
|
| 08/08/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) N/H DWV UP TO 2ND FLOOR OK 2) COLUMNS "O" TO "I" & "2" TO "8" IN WALL AND OVERHEAD |
|
| 08/05/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) NOT INSTALLED PER PLAN 2) PROVIDE REVISED APPROVED GAS PLAN 3) WELD PIPE TO BE TESTED AT 60 POUNDS ON A HUNDRED POUND GAUGE IN ONE POUND INCREMENTATION |
|
| 07/13/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ANNEX MECH ROOM 2ND LIFT ON MASONRY |
|
| 07/06/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) N/H IN CMU WALLS AT ANNEX OK |
|
| 07/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 5" N/H RAIN LEADERS UP TO 3RD FLOOR OK |
|
| 06/30/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4" N/H RAIN LEADERS UP TO THIRD FLOOR OK 2) ANNEX VENTS UP 2ND LIFT OK FOR BLOCK |
|
| 06/29/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER LINE TO VISITORS CENTER FROM OFFICE OK TO COVER |
|
| 06/24/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ANNEX MECHANICAL ROOM MASONRY WALL UP FOUR FEET |
|
| 06/21/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) AT ANNEX-PIPING IN MASONRY WRAPPED TO FOUR FEET AFF |