Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2012 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 11/23/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1 LIGHT POLE BASE NW CORNER | |
| 11/10/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) LIGHT POLE CAISSON (SOUTHEAST CORNER); PARKIHNG GARAGE NORTHWEST EXTERIOR STAIRWELL FOOTING AND PLANTER; NORTH EAST PATIO WALL FOOTING-OK TO POUR FOOTINGS |
|
| 10/31/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 80' AT NORTHWEST CORNER BY TRAILER 3 LIGHT POLE BASES |
|
| 10/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PLANTER FOOTER |
|
| 10/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 6 LIGHT POLE BASES ON WEST SIDE |
|
| 10/25/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 7 LIGHT POLE BASE ON WEST SIDE OF BLDG |
|
| 10/24/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 6 LIGHT POLE CAISSON FOOTINGS: WEST SIDE OF BLDG (SOUTH TO MID-POINT OF BLDG) OK TO POUR |
|
| 10/20/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 7 LIGHT POLE CAISSON FOOTINGS: 3 NORTH AND NORTHEAST 4 SOUTH & SOUTHEAST OK TO POUR PROGRESS AREAS |
|
| 09/21/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/19/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/16/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1) NORTH WEST CORNER OF ANNEX | |
| 09/15/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 07/27/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 05/10/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) DRY PACK PROGRESS ON COLUMNS |