Permit: T10CM02768

Parcel: 14043013B

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
04/20/2011 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
04/18/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/07/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
11/18/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*WEST RETAINING F10,I2 FOOTINGS
PROVIDE RFI 2 MATTS 4 BORS EACH
11/15/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 14 PERIMETER F4 & F3 FOOTING
2) TERRACON SPECIAL INSPECTED
11/12/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS; 3 C3/F4 FOOTINGS GL: 7/C-G; 4 C1/F6 FOOTINGS: GL: 6/B-H OK TO POUR FOOTINGS