Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date |
Description |
Inspector |
Results |
Comments |
| 06/15/2011 |
STORMWATER FOLLOW-UP INSP |
|
Approved |
Approved |
| 04/11/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place and in good cond. |
| 03/08/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Asked contractor to sweep street where trackout has occured |
| 02/25/2011 |
STORMWATER FOLLOW-UP INSP |
|
Partial Approval |
Controls have been moved and replaced, slope along eastern edge dressed up. |
| 02/09/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Met with contractor to discuss stabilizing cut slope along east property edge below new wall, and move straw bales to outlet culverts. |
| 02/08/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Need to install controls at base of slope below new wall so that soil does not enter conc. swale to the Santa Cruz. |
| 02/02/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place and in good cond. |
| 01/21/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place ned to continue to sweep streets for tract out. |