Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 11/10/2011 |
GRADING - INTERMEDIATE |
|
Approved |
|
| 10/26/2011 |
GRADING - INTERMEDIATE |
|
Continued |
NO CONCERNS AT THIS TIME. |
| 10/18/2011 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON TRASH ENCLOSURE AND LANDSCAPING |
| 06/29/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Another section of the parking lot was paved with conc. today everything looks good. |
| 06/22/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Conc. continued to be placed in parking lot. |
| 06/14/2011 |
GRADING - INTERMEDIATE |
|
Continued |
COnc paving of parking lot still underway |
| 06/08/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor working on curbing and paving |
| 04/27/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Building under constuction, no grading activity |
| 04/14/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Building still under construction, no grading activity at this time. |
| 03/22/2011 |
GRADING - INTERMEDIATE |
|
Continued |
rough grading comlpete building under construction. |
| 02/04/2011 |
GRADING - INTERMEDIATE |
|
Continued |
No construction activity at the site. |
| 01/19/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Footings for building formed no other grading activity. |
| 01/06/2011 |
GRADING - INTERMEDIATE |
|
Correction Required |
Site work underway with building pad and parking lot. No pre-con or stormwater inspection has been scheduled yet. I contacted contractor for project and they will call for an inspection on 1/7. |