Permit: T10BU01569

Parcel: 12901018M


Addresses:

191 S PLUMER AV


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T10BU01569

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
11/10/2011 GRADING - INTERMEDIATE Approved
10/26/2011 GRADING - INTERMEDIATE Continued NO CONCERNS AT THIS TIME.
10/18/2011 GRADING - INTERMEDIATE Continued WORKING ON TRASH ENCLOSURE AND LANDSCAPING
06/29/2011 GRADING - INTERMEDIATE Continued Another section of the parking lot was paved with conc. today everything looks good.
06/22/2011 GRADING - INTERMEDIATE Continued Conc. continued to be placed in parking lot.
06/14/2011 GRADING - INTERMEDIATE Continued COnc paving of parking lot still underway
06/08/2011 GRADING - INTERMEDIATE Continued Contractor working on curbing and paving
04/27/2011 GRADING - INTERMEDIATE Continued Building under constuction, no grading activity
04/14/2011 GRADING - INTERMEDIATE Continued Building still under construction, no grading activity at this time.
03/22/2011 GRADING - INTERMEDIATE Continued rough grading comlpete building under construction.
02/04/2011 GRADING - INTERMEDIATE Continued No construction activity at the site.
01/19/2011 GRADING - INTERMEDIATE Continued Footings for building formed no other grading activity.
01/06/2011 GRADING - INTERMEDIATE Correction Required Site work underway with building pad and parking lot. No pre-con or stormwater inspection has been scheduled yet. I contacted contractor for project and they will call for an inspection on 1/7.