Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2011 | GRADING - INTERMEDIATE | Approved | ||
| 06/08/2011 | GRADING - INTERMEDIATE | Continued | SPOKE WITH SUPERINTENDENT, HE WILL CALL IN FINAL INSPECTIONS NEXT WEEK. NO STORM WATER ISSEUES, NEED TO SWEEP UP TRACKED SOIL FROM CONSTRUCTION. |
|
| 06/02/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to pave parking lot, contractor will dress up some areas along the curb to insure a 6" reveal, also dig out water harvest areas to match plan. | |
| 05/26/2011 | GRADING - INTERMEDIATE | Continued | Checked portions of subgrade, verified curb cuts for water harvest areas. Contractor will pave next week. | |
| 05/12/2011 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT SITE WORK OR STORM WATER CONCERNS AT THIS TIME | |
| 04/14/2011 | GRADING - INTERMEDIATE | Continued | NO SITE WORK OTHER THAT TRASH ENCLOSURE | |
| 03/31/2011 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. NO SITE WORK AT THIS TIME | |
| 03/15/2011 | GRADING - INTERMEDIATE | Continued | CHECKED STATUS OF SITE, CONTRACTOR WORKING ON FOUDATION AND UTILITY TIE-INS, NO SITE WORK AT THIS TIME. NO STORM WATER CONCERNS AT THIS TIME |