Permit: T10BU01437

Parcel: 13711425F


Addresses:

1690 W IRVINGTON RD

Inspection Status: Continued

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
07/26/2011 STORMWATER FOLLOW-UP INSP Continued STOCK PILE MOVED FROM LOT TO THE WEST OF JOB SITE NEED TO HYDRO SEED.
07/12/2011 STORMWATER FOLLOW-UP INSP Continued WATER LINE BROKEN WORKING ON CLEAN UP.
07/07/2011 STORMWATER FOLLOW-UP INSP Continued GOT WITH DAN TO KEEP UP WITH TRACK OUT.
07/06/2011 STORMWATER FOLLOW-UP INSP Continued DAN INSTALLED ROCK AT GATE. STREET LOOKS MUCH BETTER.
07/01/2011 STORMWATER FOLLOW-UP INSP Continued CALLED DAN ABOUT CLAEN UP HE SAID HE'S WORKING ON IT.
06/23/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
05/23/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERS AT THIS TIME.
05/20/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS.
05/16/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
05/13/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
04/25/2011 STORMWATER FOLLOW-UP INSP Continued SWPPP OK AT THIS TIME.
04/21/2011 STORMWATER FOLLOW-UP INSP Continued COntrols in place and in good cond.
04/04/2011 STORMWATER FOLLOW-UP INSP Continued GOT WITH DAN ABOUT STOCK PILE IF MORE THAN A DAY OR TWO BEFORE MOVING PROIVDE SWPPP PROTECTION.
04/01/2011 STORMWATER FOLLOW-UP INSP Continued DAN NOT ON SITE. STOCK PILE HAS NOT BEEN MOVED.
03/28/2011 STORMWATER FOLLOW-UP INSP Continued GOT WITH DAN ABOUT SWPPP CONTROLS. TO INSTALL PER APROVED PLAN'S.
03/25/2011 STORMWATER FOLLOW-UP INSP Continued UNABLE TO SEE SWPPP PLANS CONTRACTOR NOT ON SITE AND TRAILER WAS LOCKED.
03/07/2011 STORMWATER FOLLOW-UP INSP Continued Controls in place and in good cond.
02/16/2011 STORMWATER FOLLOW-UP INSP Continued Controls in place and in good cond.
02/01/2011 STORMWATER FOLLOW-UP INSP Continued Street is being sweep everyother day however, there is still some track out, will need to start sweeping every day.
01/26/2011 STORMWATER FOLLOW-UP INSP Correction Required Straw waddel is installed but have trackout to water supply, I asked contractor to clean off road and sweep street.
01/24/2011 STORMWATER FOLLOW-UP INSP Correction Required Premeter controls not installed, gave untill 1/25 to get done.