Inspection Status: Continued
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date |
Description |
Inspector |
Results |
Comments |
| 09/13/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
WORKING ON RIP RAP AT DRAINS. |
| 08/19/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Approved |
|
| 06/30/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
GOT WITH DAN TO CHECK ON SWPP CONTOLS . |
| 05/31/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
NO CONCERNS. |
| 05/18/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
NO CONCERNS. |
| 05/09/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
NO CONCERNS AT THIS TIME. |
| 05/02/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
SWPPP OK AT THIS TIME. |
| 03/30/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
SWPPP CONTROLS OK. MOVING STOCK PILE THIS WEEK. |
| 01/24/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Correction Required |
Waddel delivered to site but not installed yet. spoke to Chestnut Const. and gave them untill 1/25 to get SWPP done. |
| 01/19/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Partial Approval |
Need to finish install of premeter controls and const. entrance |