Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/06/2011 | GRADING - FINAL | Approved | ALL CONCERNS ASSOCIATED WITH THE WEST RET/DET BASIN WILL BE ADDRESSED DURING THE CONSTRUCTION OF BLDG #11. | |
05/18/2011 | GRADING - FINAL | Continued | MET WITH SUPINTENDENT AND ENGINEER ON SITE. THE ENG OF RECORD WILL SIGN OFF ON THE RE/DET BASIN THAT HAS SILTED-IN, STATING THAT IS WITH IN DESIGN PERAMETERS FOR THE VOLUME OF THE BASIN. STILL NEED CERT STATEMENT AND AS-BUILT PLAN |
|
05/16/2011 | GRADING - FINAL | Cancelled | IVRS - RI canceled | |
05/13/2011 | GRADING - FINAL | Partial Approval | 1) PROVIDE AN APPROVED/ REVISED PLAN FOR FINAL INSPECTION. 2) PROVIDE A CERTIFICATION STATEMENT FROM YOUR ENG OF RECORD. 3) CLEAN OUT THE SILT FROM EXISTING RET/DET BASIN |
|
04/19/2011 | GRADING - FINAL | Denied | MINIMAL SITE WORK LEFT TO BE COMPLETED. RAILING ALONG EAST SIDEWALK AT NORTH BLDG. SIDEWALK ON NORTH SIDE OF SOUTH BLDG. LANDSCAPING AROUND BOTH BLDGS. STABILIZE EMPTY LOT BETWEEN BOTH BLDGS. CERTILFICATION STATEMENT FROM EOR. |
|
03/28/2011 | GRADING - FINAL | Denied | CHANGES TO PEDESTRIAN ACCESS ALONG NW CORNER OF SITE, MUST BE SHOWN ON APPROVED PLAN. NO STORM WATER CONCERNS AT THIS TIME. ENSURE THE ENGINEER OF RECORD CERTIFIES THAT ALL RET/DET BASINS ARE AT PROPER SIZE AND VOLUME AND FUNCTION THE WAY THEY WERE DESIGNED TO, PRIOR TO FINAL APPROVAL. |